Work Description
2025 WILDFIRE REBUILD, NEW SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND ACCESSORY DWELLING UNIT PER GCS 66323(a)(1), 1-STORY, 70'-6" x 38'-7". NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 KEVIN MORALES
Corrections Issued 8/19/2025 KEVIN MORALES
Quality Review Completed 8/19/2025 EUGENE BARBEAU
Plan Check Approved 9/23/2025 KEVIN MORALES
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/19/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/19/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/19/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/19/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 8/25/2025 PATRICK PEREZ

Contact Information

Contractor Good Life Home Design Inc; Lic. No.: 1094738-B       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2025 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 11/12/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 1/23/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 No Access for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Conditional Approval TEMISTOCLES CAAL
Deputy Drilled-In Anchors 4/9/2026 Conditional Approval JUAN VALENZUELA
HVAC-Rough 5/13/2026 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 5/21/2026 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 5/21/2026 Approved TEMISTOCLES CAAL
PLUMBING-Rough 5/21/2026 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 5/22/2026 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 Partial Approval EVAN COOPER