15276 W DE PAUW ST 90272

Certificate Information: 15276 W DE PAUW ST 90272

Application / Permit
25010-10000-03207
Plan Check / Job No.
B25LA29777
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO8 SOLAR INSTALLATION EXEMPT PER GOVEROR'S ORDER N-29-25
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
Issued on 9/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 VIVIAN LAO
Corrections Issued 7/25/2025 VIVIAN LAO
Quality Review Completed 7/25/2025 JOHN FRANCIA
Plan Check Approved 9/4/2025 VIVIAN LAO
Issued 9/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/28/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/28/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 7/28/2025 JESSICA OPINION
Sewer availability Cleared 7/28/2025 JESSICA OPINION
Hydrant and Access approval Cleared 8/19/2025 JERRY KAO
Coastal Zone Cleared 8/28/2025 BRENNEN OBETO
Coastal Zone Cleared 8/28/2025 BRENNEN OBETO
Coastal Zone Cleared 8/28/2025 BRENNEN OBETO

Contact Information

Contractor Lee David; Lic. No.: 1105609-B       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2025 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 11/7/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/7/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 11/13/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 12/8/2025 Partial Approval STEPHANIE SWANSON
Insulation 12/9/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 3/4/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 3/4/2026 Not Ready for Inspection DANIEL VERA
Gas Test 3/6/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 3/6/2026 Corrections Issued DANIEL VERA
ELECTRICAL-Rough 3/9/2026 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 3/10/2026 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 3/17/2026 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/17/2026 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 3/23/2026 Conditional Approval STEPHANIE SWANSON
HVAC-Rough 3/23/2026 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 3/23/2026 Approved STEPHANIE SWANSON
HVAC-Rough 3/27/2026 Conditional Approval EVAN COOPER
Insulation 3/31/2026 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 3/31/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 4/2/2026 Approved STEPHANIE SWANSON
Green Building Rough 4/2/2026 Approved STEPHANIE SWANSON
Insulation 4/2/2026 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 4/2/2026 Partial Approval STEPHANIE SWANSON
Verify Sprinkler Sign Off 4/2/2026 Approved STEPHANIE SWANSON
Drywall Nailing 4/6/2026 Not Ready for Inspection BOBBY KEY
Insulation 4/6/2026 Approved BOBBY KEY
Drywall Nailing 4/9/2026 Conditional Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/18/2026 Approved STEPHANIE SWANSON