5314 S LATHAM ST 90011
Certificate Information: 5314 S LATHAM ST 90011
- Application / Permit
- 25010-10000-03174
- Plan Check / Job No.
- B25LA29426
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22.A.33(b)(1) AT THE REAR OF PROPERTY
- Permit Issued
- Issued on 10/16/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | MIGUEL LOPEZ |
| Corrections Issued | 8/8/2025 | MIGUEL LOPEZ |
| Quality Review Completed | 8/11/2025 | KESETE HAREGOT |
| Building Plans Picked Up | 8/19/2025 | APPLICANT |
| Applicant returned to address corrections | 9/10/2025 | MIGUEL LOPEZ |
| Plan Check Approved | 9/15/2025 | MIGUEL LOPEZ |
| Issued | 10/16/2025 | APPLICANT |
| CofO in Progress | 4/30/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/27/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/27/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 9/8/2025 | GILBERT URREA |
Contact Information
| Contractor | Mateos Construction & Remodeling Co; Lic. No.: 1034279-B | 10378 MARKLEIN AVE MISSION HILLS, CA 91345 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/18/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/18/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/18/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/18/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Rough | 12/18/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 12/18/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 12/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/24/2025 | Corrections Issued | LUIS CASTRO |
| Insulation | 12/24/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 12/24/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 1/7/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 1/7/2026 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/7/2026 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 1/7/2026 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 1/9/2026 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 1/9/2026 | Approved | LUIS CASTRO |
| Insulation | 1/12/2026 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/13/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 1/20/2026 | Approved | ALEX COLIN |
| Gas Test | 3/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 3/31/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 4/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/10/2026 | Approved | RAUL BARAJAS |
| Final | 4/10/2026 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 4/10/2026 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 4/10/2026 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 4/10/2026 | Approved | RAUL BARAJAS |
| Service/Power Release | 4/10/2026 | Partial Inspection | RAUL BARAJAS |
| Smoke Detectors | 4/10/2026 | Approved | RAUL BARAJAS |
| Final | 4/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/24/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/29/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/29/2026 | Approved | ALEJANDRO DE ARTOLA |