12965 W RUBENS AVE 90066
Certificate Information: 12965 W RUBENS AVE 90066
- Application / Permit
- 25010-10000-03159
- Plan Check / Job No.
- B25LA29320
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO (N) ADU PER GC 66323(a)(1)
- Permit Issued
- Issued on 10/26/2025
- Issuing Office
- Current Status
- Issued on 10/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/23/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/23/2025 | SERGIO MUNIZ |
| Plan Check Approved | 10/25/2025 | ALEC MOUSAKHANIAN |
| Issued | 10/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2025 | CHRISTINE REUSCH |
| Construction near power lines | Cleared | 10/10/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/10/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/15/2025 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/16/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/16/2025 | Approved | ANTHONY EGSON |
| Sewer | 12/16/2025 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/22/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/20/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 1/20/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/20/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/2/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/2/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 2/2/2026 | Approved | ANTHONY EGSON |
| Insulation | 2/9/2026 | Corrections Issued | JESUS PINEDA |
| Wood Frame | 2/17/2026 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 2/20/2026 | Approved | ANTHONY EGSON |
| Insulation | 2/20/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/18/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/5/2026 | Approved | MORRIS JACKSON |
| Final | 6/5/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 6/5/2026 | Approved | MORRIS JACKSON |
| MERV13>=Final | 6/5/2026 | Approved | MORRIS JACKSON |
| MERV13>=Rough | 6/5/2026 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 6/5/2026 | Approved | MORRIS JACKSON |