1130 N EMBURY ST 90272

Certificate Information: 1130 N EMBURY ST 90272

Application / Permit
25010-10000-03132
Plan Check / Job No.
B25LA29016
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING. NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 9/8/2025
Issuing Office
Current Status
Issued on 9/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 HERNAN ARREOLA
Corrections Issued 8/4/2025 HERNAN ARREOLA
Quality Review Completed 8/6/2025 CHAD DOI
Plan Check Approved 9/5/2025 HERNAN ARREOLA
Issued 9/8/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2025 JOHN LIN
Roof/Waste drainage to street Cleared 8/4/2025 JOHN LIN
Sewer availability Cleared 8/4/2025 JOHN LIN
Hydrant and Access approval Cleared 8/27/2025 LAVEON RIDER

Contact Information

Architect Kudelka,, Phillip Roman; Lic. No.: NA19548       ,
Contractor Par Construction Inc; Lic. No.: 983593-B       ,
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 1/28/2026 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 2/3/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 2/9/2026 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 2/9/2026 Approved TEMISTOCLES CAAL
Sewer 2/9/2026 Approved TEMISTOCLES CAAL
Deputy Reinf. Concrete 2/10/2026 Conditional Approval TEMISTOCLES CAAL
Deputy Wood Construction 3/2/2026 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 Not Ready for Inspection MICHAEL ALLEN
Green Building Rough 4/7/2026 Not Ready for Inspection MICHAEL ALLEN
Verify Sprinkler Sign Off 4/7/2026 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Not Ready for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Not Ready for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Approved TEMISTOCLES CAAL
Pre-Inspection 5/20/2026 Partial Inspection TEMISTOCLES CAAL
HVAC-Rough 5/22/2026 Corrections Issued EVAN COOPER
PLUMBING-Rough 5/26/2026 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 5/29/2026 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/29/2026 Corrections Issued ARAM AVEDISIAN
Green Building Rough 5/29/2026 Approved ARAM AVEDISIAN
HVAC-Rough 5/29/2026 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 5/29/2026 Corrections Issued ARAM AVEDISIAN
Verify Sprinkler Sign Off 5/29/2026 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/3/2026 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 6/3/2026 Approved TEMISTOCLES CAAL
Insulation 6/3/2026 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Final 6/3/2026 Corrections Issued TEMISTOCLES CAAL
Drywall Nailing 6/12/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 6/12/2026 Approved TEMISTOCLES CAAL
Shower Pan 6/12/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 6/24/2026 Approved JESUS PINEDA