844 N CHAUTAUQUA BLVD 90272
Certificate Information: 844 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 25010-10000-03107
- Plan Check / Job No.
- B25LA28810
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH BASEMENT, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 10/2/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | KEVIN MORALES |
| Corrections Issued | 7/22/2025 | KEVIN MORALES |
| Quality Review Completed | 7/22/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/9/2025 | KEVIN MORALES |
| Plan Check Approved | 9/24/2025 | KEVIN MORALES |
| Issued | 10/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/22/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 8/1/2025 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 8/5/2025 | JOHN CONNEALLY |
Contact Information
| Architect | Cichowski,, Joel Brennan; Lic. No.: NA30916 | , |
| Contractor | Bohler Builders Group Inc; Lic. No.: 957685-B | , |
| Engineer | Jacobs,, Scott E; Lic. No.: NA60019 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Reinforced Concrete Frame | 7/23/2026 Time Frame: 12-2 |
Inspection Request History
| Pre-Inspection | 10/20/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Piling/Pier/Caisson | 1/23/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 1/27/2026 | Conditional Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 1/30/2026 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/25/2026 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 3/3/2026 | Partial Approval | MICHAEL ALLEN |
| Deputy Reinf. Concrete | 3/5/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/6/2026 | Partial Approval | TEMISTOCLES CAAL |
| Reinforced Concrete Frame | 3/17/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Shotcrete | 3/18/2026 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 4/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 4/6/2026 | Partial Approval | DANIEL VERA |
| Underground Mechanical | 4/16/2026 | Partial Approval | MEL KHACHATOURIAN |
| Pre-Inspection | 4/30/2026 | Partial Inspection | TEMISTOCLES CAAL |
| Structural Steel Frame | 5/18/2026 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 5/19/2026 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 5/19/2026 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/19/2026 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 5/19/2026 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/22/2026 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/22/2026 | Partial Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 6/29/2026 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 6/29/2026 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 6/29/2026 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/30/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 6/30/2026 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/30/2026 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 6/30/2026 | Partial Inspection | JESUS PINEDA |
| Reinforced Concrete Frame | 7/10/2026 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 7/10/2026 | Partial Inspection | JESUS PINEDA |