17041 W BOLLINGER DR 90272
Certificate Information: 17041 W BOLLINGER DR 90272
- Application / Permit
- 25010-10000-03082
- Plan Check / Job No.
- B25LA28634
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 10/22/2025
- Issuing Office
- Current Status
- Issued on 10/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | JOHNNY WU |
| Corrections Issued | 8/6/2025 | JOHNNY WU |
| Quality Review Completed | 8/12/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/15/2025 | JOHNNY WU |
| Applicant returned to address corrections | 10/22/2025 | JOHNNY WU |
| Plan Check Approved | 10/22/2025 | JOHNNY WU |
| Issued | 10/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Permit | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 8/20/2025 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 8/22/2025 | ORVAL HERNANDEZ-MARCI |
| Construction near power lines | Cleared | 9/22/2025 | ENRIQUE ACOSTA |
| Miscellaneous | Cleared | 10/22/2025 | JOHNNY WU |
Contact Information
| Architect | , ; Lic. No.: C37124 | 1734 WILCOX AVENUE LOS ANGELES, CA 90028 |
| Contractor | Johnson N S Company; Lic. No.: 455830-B | , |
| Engineer | Yenjai,, Seree; Lic. No.: NA73151 | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2025 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 12/16/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Partial Approval | BOBBY KEY |
| Reinforced Concrete Frame | 1/20/2026 | Partial Approval | BOBBY KEY |
| Masonry Wall/Backfill | 2/11/2026 | No Access for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Partial Approval | BOBBY KEY |
| Piling/Pier/Caisson | 3/23/2026 | Not Ready for Inspection | DANIEL VERA |
| Piling/Pier/Caisson | 3/25/2026 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 4/14/2026 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 4/29/2026 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 5/19/2026 | Partial Approval | DANIEL VERA |
| Structural Steel Frame | 5/19/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2026 | Partial Approval | DANIEL VERA |
| Green Building Rough | 5/22/2026 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/22/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2026 | Partial Approval | DANIEL VERA |
| Sewer | 5/27/2026 | Approved | DANIEL VERA |