2021 W 28TH ST 1-4 90018

Certificate Information: 2021 W 28TH ST 1-4 90018

Application / Permit
25010-10000-03070
Plan Check / Job No.
B25LA28479
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) 2-STORY - 4 ADUS. DETACHED ADUs PER 66323(a)(4). TO BE EQUIPPED WITH NFPA13R FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 4/20/2026
Issuing Office
Current Status
Issued on 4/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 ADRIANA LOPEZ
Corrections Issued 8/20/2025 ADRIANA LOPEZ
Quality Review Completed 8/29/2025 HERNAN ARREOLA
Applicant returned to address corrections 11/18/2025 ADRIANA LOPEZ
Applicant returned to address corrections 12/9/2025 ADRIANA LOPEZ
Applicant returned to address corrections 1/8/2026 ADRIANA LOPEZ
Applicant returned to address corrections 2/2/2026 ADRIANA LOPEZ
Applicant returned to address corrections 3/3/2026 ADRIANA LOPEZ
Plan Check Approved 4/16/2026 ADRIANA LOPEZ
Issued 4/20/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/7/2025 DERRICK MAGEE
CPC Cleared 9/8/2025 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 9/9/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 9/9/2025 DERRICK MAGEE
Sewer availability Cleared 9/9/2025 DERRICK MAGEE
Hydrant and Access approval Cleared 10/24/2025 RUEL COLE
HPOZ Cleared 12/9/2025 DANIEL MATA
ZI Cleared 12/9/2025 DANIEL MATA
Green Code Cleared 1/12/2026 ADRIANA LOPEZ
DAS Clearance Cleared 1/14/2026 ADRIANA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2026 Approved JAMES POWERS
Pre-Inspection 5/7/2026 Partial Approval JAMES POWERS
Green Building Rough 6/3/2026 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/3/2026 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/3/2026 Not Ready for Inspection JAMES POWERS
Wood Frame 6/3/2026 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/18/2026 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 6/18/2026 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/18/2026 OK to Expire Permit JAMES POWERS
Footing/Foundation/Slab 6/22/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2026 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/23/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/23/2026 Partial Approval JAMES POWERS
Green Building Rough 6/23/2026 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 6/23/2026 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/23/2026 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/23/2026 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 6/30/2026 Conditional Approval JOEY BUCHANAN
Deputy Methane Barrier 7/9/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/13/2026 Partial Approval JAMES POWERS
METHANE-Barrier 7/13/2026 Approved JAMES POWERS
METHANE-Subgrade 7/13/2026 Approved JAMES POWERS