4550 N RUBIO AVE 91436
Certificate Information: 4550 N RUBIO AVE 91436
- Application / Permit
- 25010-10000-03024
- Plan Check / Job No.
- B25LA27966
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. New 2 Story SFD WITH 2 CAR ATTACH GARAGE
- Permit Issued
- Issued on 9/29/2025
- Issuing Office
- Current Status
- Issued on 9/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | VARAND SARKISIAN |
| Assigned to Zoning Architect | 7/10/2025 | DAVID ZHENG |
| Corrections Issued | 7/16/2025 | VARAND SARKISIAN |
| Quality Review Completed | 7/21/2025 | GARO TELMI |
| Plan Check Approved | 9/11/2025 | VARAND SARKISIAN |
| No Progress | 9/11/2025 | VARAND SARKISIAN |
| Plan Check Approved | 9/29/2025 | VARAND SARKISIAN |
| Issued | 9/29/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/31/2025 | JOHN CONNEALLY |
| Address approval | Cleared | 8/1/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/1/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 8/1/2025 | RYAN CASTRO |
| Watercourse | Cleared | 8/4/2025 | RYAN CASTRO |
| Trees in Parkway | Cleared | 8/25/2025 | RICHARD SANCHEZ |
| Permit | Cleared | 9/2/2025 | MICHAEL BROWN |
| Zoning Plan Check | Cleared | 9/2/2025 | DAVID ZHENG |
| Grading Pre-Inspection | Cleared | 9/11/2025 | VARAND SARKISIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/19/2025 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 12/19/2025 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/5/2026 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/8/2026 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 2/25/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 3/2/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/4/2026 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 3/4/2026 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/9/2026 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 3/9/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/9/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 3/9/2026 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | THOMAS FINNILA |
| Insulation | 3/11/2026 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | THOMAS FINNILA |
| Drywall Nailing | 3/18/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/18/2026 | Partial Approval | ALEXANDER HANDY |