3967 1/2 S 3RD AVE 90008

Certificate Information: 3967 1/2 S 3RD AVE 90008

Application / Permit
25010-10000-02987
Plan Check / Job No.
B25LA27717
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 9/19/2025
Issuing Office
Metro
Current Status
Issued on 9/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/3/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 JAD BASMA
Corrections Issued 7/13/2025 JAD BASMA
Quality Review Completed 7/17/2025 KEN GILL
Building Plans Picked Up 7/18/2025 APPLICANT
Plan Check Approved 8/19/2025 JAD BASMA
Issued 9/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/15/2025 CINDY QI
Roof/Waste drainage to street Cleared 7/15/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/7/2025 CINDY QI
Sewer availability Cleared 8/7/2025 CINDY QI

Contact Information

Contractor Cgs Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/9/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 10/9/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 2/3/2026 Approved LUIS CASTRO
HVAC-Rough 2/3/2026 Corrections Issued LUIS CASTRO
PLUMBING-Rough 2/3/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/5/2026 Approved LUIS CASTRO
Green Building Rough 2/5/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 2/5/2026 Partial Approval LUIS CASTRO
Verify Sprinkler Sign Off 2/5/2026 Approved LUIS CASTRO
Insulation 2/13/2026 Approved MICHAEL LEWIS
Drywall Nailing 2/23/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 3/6/2026 Approved LUIS CASTRO
Shower Pan 3/6/2026 Approved LUIS CASTRO
Sewer 4/29/2026 Approved LUIS CASTRO
Underground Mechanical 5/1/2026 Partial Approval LUIS CASTRO