654 N EL MEDIO AVE 90272

Certificate Information: 654 N EL MEDIO AVE 90272

Application / Permit
25010-10000-02969
Plan Check / Job No.
B25LA27504
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE,
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
Issued on 9/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2025 APPLICANT
Assigned to Plan Check Engineer 7/14/2025 KEVIN MORALES
Corrections Issued 7/16/2025 KEVIN MORALES
Quality Review Completed 7/18/2025 JOSE RODRIGUEZ
Plan Check Approved 9/11/2025 KEVIN MORALES
Issued 9/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/16/2025 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/16/2025 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/16/2025 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/16/2025 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 8/27/2025 KURT CORRAL

Contact Information

Architect Palka,, Joseph Anthony; Lic. No.: NA24276       ,
Contractor Owner-Builder       ,
Engineer Cox,, Steven Jeffrey; Lic. No.: NA48940       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Gas Test 7/10/2026   
PLUMBING-Rough 7/10/2026   

Inspection Request History

ELECTRICAL-Rough 11/4/2025 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 11/4/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 11/6/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 12/11/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 12/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
Gas Test 12/11/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 12/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 12/11/2025 Partial Approval MEL KHACHATOURIAN
Verify Sprinkler Sign Off 12/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 1/15/2026 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval MEL KHACHATOURIAN
Green Building Rough 1/15/2026 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 1/15/2026 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 2/12/2026 Partial Approval MEL KHACHATOURIAN
Gas Test 2/12/2026 Approved MEL KHACHATOURIAN
HVAC-Rough 2/12/2026 Approved MEL KHACHATOURIAN
PLUMBING-Rough 2/12/2026 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/13/2026 Approved MEL KHACHATOURIAN
Green Building Rough 3/13/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 3/13/2026 Partial Approval MEL KHACHATOURIAN
Verify Sprinkler Sign Off 3/13/2026 Approved MEL KHACHATOURIAN
Insulation 3/27/2026 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 4/1/2026 Approved MICHAEL ALLEN
Drywall Nailing 4/6/2026 Approved JUAN VALENZUELA
Shower Pan 5/21/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/1/2026 Approved MEL KHACHATOURIAN
Sewer 6/4/2026 Approved MEL KHACHATOURIAN