1907 W 41ST DR 90062
Certificate Information: 1907 W 41ST DR 90062
- Application / Permit
- 25010-10000-02895
- Plan Check / Job No.
- B25LA26906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW STORAGE SHED PER WFPP
- Permit Issued
- Issued on 11/4/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2025 | LUKE GONZALES |
| Corrections Issued | 6/27/2025 | LUKE GONZALES |
| Applicant returned to address corrections | 7/3/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 11/4/2025 | EDWIN MARTINEZ |
| Issued | 11/4/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/13/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | TREVOR QUAN |
| City Hist. Cultural Monument | Cleared | 7/22/2025 | RAFAEL FONTES |
| Historic monument | Cleared | 7/22/2025 | RAFAEL FONTES |
| Construction near power lines | Cleared | 8/28/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/21/2025 | Approved | SABAS ALONSO |
| Sewer | 11/21/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 11/21/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 4/8/2026 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/8/2026 | Approved | SABAS ALONSO |