815-815 1/2 E 111TH PL 90059
Certificate Information: 815-815 1/2 E 111TH PL 90059
- Application / Permit
- 25010-10000-02874
- Plan Check / Job No.
- B25LA26696
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN. NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE. NFPA-13D SPRINKLERS THRU-OUT
- Permit Issued
- Issued on 3/24/2026
- Issuing Office
- Current Status
- Issued on 3/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | PRANITA SHAH |
| Assigned to Zoning Architect | 7/3/2025 | AMIR NAKHLA |
| Corrections Issued | 7/7/2025 | PRANITA SHAH |
| Quality Review Completed | 7/16/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/24/2025 | PRANITA SHAH |
| Plan Check Approved | 2/4/2026 | PRANITA SHAH |
| Issued | 3/24/2026 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/21/2025 | ERNEST TSE |
| Address approval | Cleared | 7/26/2025 | CELINA MORENO |
| Highway dedication | Cleared | 7/26/2025 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 7/28/2025 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/29/2025 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 11/21/2025 | CELINA MORENO |
| Sewer availability | Cleared | 12/3/2025 | CELINA MORENO |
| SB8 RUD | Cleared | 12/9/2025 | JASON WELLS |
| Zoning Plan Check | Cleared | 12/19/2025 | AMIR NAKHLA |
Contact Information
| Contractor | Kn Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/13/2026 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 4/22/2026 | Approved | ARTHUR NEGRETE |
| Wood Frame | 4/22/2026 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 4/23/2026 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/15/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/15/2026 | Approved | EUGENE CASSIDY |
| Sewer | 5/15/2026 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/15/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/19/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 5/19/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 5/19/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/19/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 5/19/2026 | No Access for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | BEN MOLSTAD |
| Green Building Rough | 5/22/2026 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/22/2026 | Partial Approval | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 5/22/2026 | Approved | BEN MOLSTAD |
| Insulation | 5/26/2026 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/3/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/3/2026 | Approved | ARTHUR NEGRETE |