110 N MAPLETON DR 90077

Certificate Information: 110 N MAPLETON DR 90077

Application / Permit
25010-10000-02833
Plan Check / Job No.
B25LA26328
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
EPLAN. PROPOSED (N) 220 SQ. FT. GUARDHOUSE
Permit Issued
Issued on 3/16/2026
Issuing Office
Current Status
Issued on 3/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 VARAND SARKISIAN
Corrections Issued 7/8/2025 VARAND SARKISIAN
Quality Review Completed 7/23/2025 PRANITA SHAH
Applicant returned to address corrections 9/17/2025 VARAND SARKISIAN
Plan Check Approved 3/12/2026 VARAND SARKISIAN
Issued 3/16/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/1/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/1/2025 LEE GUILBEAUX
Sewer availability Cleared 8/1/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/1/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/8/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/13/2025 JERRY KAO
Encroachment in public way Cleared 2/26/2026 CHRISTINE REUSCH
ZA Case Cleared 3/4/2026 DANIEL CORONADO
Grading Pre-Inspection Cleared 3/12/2026 VARAND SARKISIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2026 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/28/2026 Approved RYAN SALAZAR