15272 W DE PAUW ST 90272

Certificate Information: 15272 W DE PAUW ST 90272

Application / Permit
25010-10000-02825
Plan Check / Job No.
B25LA24410
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
*2025 WILDFIRE ELIGIBLE PROJECT PER EO1**EPLAN* NEW 1-STORY DETACHED 2-CAR GARAGE.
Permit Issued
Issued on 10/27/2025
Issuing Office
Current Status
Issued on 10/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 VIVIAN LAO
Corrections Issued 6/24/2025 VIVIAN LAO
Quality Review Completed 6/24/2025 JOHN FRANCIA
Applicant returned to address corrections 7/15/2025 VIVIAN LAO
Applicant returned to address corrections 7/29/2025 VIVIAN LAO
Applicant returned to address corrections 8/6/2025 VIVIAN LAO
Applicant returned to address corrections 8/7/2025 VIVIAN LAO
Applicant returned to address corrections 10/8/2025 VIVIAN LAO
Plan Check Approved 10/27/2025 VIVIAN LAO
Issued 10/27/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2025 CELINA MORENO
Sewer availability Cleared 6/25/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 7/3/2025 CINDY QI
Hydrant and Access approval Cleared 8/15/2025 LAVEON RIDER

Contact Information

Architect Oreck,, Kevin Robert; Lic. No.: NA23895       ,
Contractor Lannen Construction Inc; Lic. No.: 811038-B       ,
Engineer Jung,, Jason; Lic. No.: NA80569       ,
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/30/2025 Partial Inspection STEPHANIE SWANSON
Pre-Inspection 11/3/2025 Partial Inspection KENNETH NAGLE
PLUMBING-Rough 12/1/2025 Partial Approval STEPHANIE SWANSON
Sewer 12/1/2025 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/4/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/4/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/11/2025 Approved STEPHANIE SWANSON
Deputy Wood Construction 1/28/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 3/20/2026 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 3/20/2026 Conditional Approval STEPHANIE SWANSON
Green Building Rough 3/20/2026 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/20/2026 Approved STEPHANIE SWANSON
Drywall Nailing 4/7/2026 Approved EVAN COOPER