626 N RADCLIFFE AVE 90272
Certificate Information: 626 N RADCLIFFE AVE 90272
- Application / Permit
- 25010-10000-02814
- Plan Check / Job No.
- B25LA26185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/16/2025
- Issuing Office
- Current Status
- Issued on 9/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2025 | STARR CHEN |
| Corrections Issued | 7/1/2025 | STARR CHEN |
| Quality Review Completed | 7/1/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/21/2025 | STARR CHEN |
| Applicant returned to address corrections | 8/28/2025 | STARR CHEN |
| Plan Check Approved | 9/11/2025 | STARR CHEN |
| Issued | 9/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/2/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 8/22/2025 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 8/25/2025 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Schondorf Enterprises Inc; Lic. No.: 1036347-B | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/9/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/31/2025 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/4/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/5/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Partial Approval | HERBERT GIRON |