708 N SWARTHMORE AVE 90272

Certificate Information: 708 N SWARTHMORE AVE 90272

Application / Permit
25010-10000-02813
Plan Check / Job No.
B25LA26182
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
Permit Issued
Issued on 9/16/2025
Issuing Office
Current Status
Issued on 9/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/26/2025 APPLICANT
Assigned to Plan Check Engineer 6/27/2025 VU NGUYEN
Corrections Issued 6/30/2025 VU NGUYEN
Quality Review Completed 7/1/2025 EUGENE BARBEAU
Applicant returned to address corrections 9/12/2025 VU NGUYEN
Plan Check Approved 9/16/2025 VU NGUYEN
Issued 9/16/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/1/2025 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/1/2025 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/1/2025 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/1/2025 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/1/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/1/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 7/1/2025 ADRIAN SANCHEZ
Sewer availability Cleared 7/1/2025 ADRIAN SANCHEZ
CPC Cleared 7/10/2025 BRENNEN OBETO
CPC Cleared 7/10/2025 BRENNEN OBETO
Miscellaneous Cleared 7/10/2025 BRENNEN OBETO
Hydrant and Access approval Cleared 7/15/2025 JERRY KAO
Miscellaneous Cleared 8/1/2025 NOAH MCCOY
GPI Written Notices Cleared 9/12/2025 VU NGUYEN
Grading Pre-Inspection Cleared 9/12/2025 VU NGUYEN

Contact Information

Architect Hoefler,, Matthew; Lic. No.: NA41026       ,
Contractor Build Method Construction Inc; Lic. No.: 1059684-B 4252 WHITSETT AVE STE 404      STUDIO CITY, CA 91604
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/5/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/8/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 12/17/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 2/27/2026 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 3/5/2026 Corrections Issued MICHAEL ALLEN
HVAC-Rough 3/5/2026 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 3/5/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 3/17/2026 Approved Pending GreenApproval STEPHANIE SWANSON
ELECTRICAL-Rough 3/17/2026 Partial Approval STEPHANIE SWANSON
Green Building Rough 3/17/2026 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 3/17/2026 Approved STEPHANIE SWANSON
Sewer 3/17/2026 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 3/17/2026 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/7/2026 Approved EVAN COOPER
Shower Pan 4/7/2026 Approved EVAN COOPER
Insulation 4/10/2026 Partial Approval DANIEL VERA
Drywall Nailing 4/15/2026 Approved STEPHANIE SWANSON
Insulation 4/15/2026 Approved STEPHANIE SWANSON