1723 S CORINTH AVE 1-42 90025

Certificate Information: 1723 S CORINTH AVE 1-42 90025

Application / Permit
25010-10000-02800
Plan Check / Job No.
B25LA26000
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan - SITE GRADING FOR PROPOSED APARTMENT UNDER 24010 10000 04657
Permit Issued
Issued on 1/21/2026
Issuing Office
Current Status
Issued on 1/21/2026

Permit Application Status History

Submitted 6/24/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 STARR CHEN
Corrections Issued 7/1/2025 STARR CHEN
Quality Review Completed 7/1/2025 EUGENE BARBEAU
Applicant returned to address corrections 10/15/2025 STARR CHEN
Plan Check Approved 1/21/2026 STARR CHEN
Issued 1/21/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/18/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/24/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 12/4/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 12/15/2025 DAVID LOPEZ

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: NA30005       ,
Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Jardine, Prouty, Kyle Addison; Lic. No.: C95048 2239 STATE AVE   UNIT B    COSTA MESA, CA 92627

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/23/2026 Partial Approval JOHNNY MIRANDA
Bottom/Toe 1/30/2026 Partial Approval JOHNNY MIRANDA
Deputy Grading 2/2/2026 Conditional Approval JOHNNY MIRANDA
Excavation 2/2/2026 Partial Approval JESUS RODRIGUEZ
Deputy Grading 2/3/2026 Conditional Approval JESUS RODRIGUEZ
Deputy Grading 2/4/2026 Partial Approval JOHNNY MIRANDA
Initial Grading 2/4/2026 Partial Approval JOHNNY MIRANDA
Deputy Grading 2/5/2026 Conditional Approval JOHNNY MIRANDA
Bottom/Toe 2/6/2026 Partial Approval JOHNNY MIRANDA
Deputy Grading 2/6/2026 Conditional Approval JOHNNY MIRANDA
Initial Grading 2/6/2026 Partial Approval JOHNNY MIRANDA
Deputy Grading 2/9/2026 Conditional Approval JOHNNY MIRANDA
Deputy Grading 2/10/2026 Conditional Approval JOHNNY MIRANDA
Excavation 2/10/2026 Partial Approval JOHNNY MIRANDA
Initial Grading 2/10/2026 Corrections Issued JOHNNY MIRANDA
Deputy Grading 2/11/2026 Conditional Approval JOHNNY MIRANDA
Deputy Grading 2/12/2026 Conditional Approval JOHNNY MIRANDA
Deputy Grading 2/13/2026 Conditional Approval JOHNNY MIRANDA
Bottom/Toe 2/25/2026 Partial Approval JESUS RODRIGUEZ
Deputy Grading 2/25/2026 Partial Approval JESUS RODRIGUEZ
Deputy Grading 2/26/2026 Conditional Approval JOHNNY MIRANDA
Deputy Grading 2/27/2026 Conditional Approval JOHNNY MIRANDA
Deputy Grading 3/4/2026 Conditional Approval LANNY MERRICK
Excavation 3/4/2026 Approved LANNY MERRICK
Deputy Grading 3/5/2026 Conditional Approval JESUS RODRIGUEZ
Approved Compaction Report 4/7/2026 Approved GERMAN RODRIGUEZ MENDOZA