735 N CHAUTAUQUA BLVD 90272
Certificate Information: 735 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 25010-10000-02744
- Plan Check / Job No.
- B25LA25493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Current Status
- Issued on 8/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | SELLA BENYAMIN |
| Corrections Issued | 6/26/2025 | SELLA BENYAMIN |
| Quality Review Completed | 6/27/2025 | STEVEN KIM |
| Plan Check Approved | 7/31/2025 | SELLA BENYAMIN |
| Issued | 8/1/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2025 | VISHAL MANDALIA |
| Sewer availability | Cleared | 6/30/2025 | VISHAL MANDALIA |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 7/22/2025 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/28/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/24/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 1/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 2/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Corrections Issued | DANIEL VERA |
| Interior/Exterior Lathing | 3/5/2026 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/18/2026 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 3/19/2026 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 4/1/2026 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 4/1/2026 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/1/2026 | Partial Approval | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 4/1/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/8/2026 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/9/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 4/9/2026 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/9/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/10/2026 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/10/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Rough | 4/10/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/10/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 4/10/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/22/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Drywall Nailing | 4/27/2026 | Approved | JUAN VALENZUELA |
| Shower Pan | 5/11/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/10/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/24/2026 | Approved | TEMISTOCLES CAAL |