406 N BEIRUT AVE 90272
Certificate Information: 406 N BEIRUT AVE 90272
- Application / Permit
- 25010-10000-02726
- Plan Check / Job No.
- B25LA25332
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | RARES BODEA |
| Corrections Issued | 6/26/2025 | RARES BODEA |
| Quality Review Completed | 6/27/2025 | STEVEN KIM |
| Applicant returned to address corrections | 7/8/2025 | RARES BODEA |
| Applicant returned to address corrections | 7/22/2025 | RARES BODEA |
| Applicant returned to address corrections | 7/24/2025 | RARES BODEA |
| Applicant returned to address corrections | 8/11/2025 | RARES BODEA |
| Plan Check Approved | 8/13/2025 | RARES BODEA |
| Issued | 8/13/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | STEPHANIE SWANSON |
| Permit Finaled | 5/13/2026 | RICHARD STEINBACH |
| CofO Issued | 5/13/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/13/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/2/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/2/2025 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 8/12/2025 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | Christiansen,, Scott; Lic. No.: NA37989 | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Conditional Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/25/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/31/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/13/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 11/13/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/11/2025 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 12/11/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/12/2025 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 12/26/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 12/26/2025 | Approved | DANIEL VERA |
| Insulation | 12/29/2025 | Approved | KENNETH NAGLE |
| Drywall Nailing | 1/21/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/21/2026 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 1/21/2026 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/21/2026 | Approved | STEPHANIE SWANSON |
| Shower Pan | 1/21/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/26/2026 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/3/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 4/9/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 4/9/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 4/9/2026 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/15/2026 | Approved | STEPHANIE SWANSON |
| Final | 4/15/2026 | Partial Inspection | STEPHANIE SWANSON |
| HVAC-Final | 4/15/2026 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 4/15/2026 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 4/15/2026 | Approved | STEPHANIE SWANSON |
| Final | 5/13/2026 | OK to Issue CofO | STEPHANIE SWANSON |