3570 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3570 S MOUNTAIN VIEW AVE 90066

Application / Permit
25010-10000-02719
Plan Check / Job No.
B25LA25271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED ACCESSORY DWELLING UNITER PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k) . ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/16/2025
Issuing Office
Current Status
Issued on 12/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/23/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 6/24/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 8/12/2025 ARAMIK SHAHMIRZAIAN
No Progress 8/20/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 8/20/2025 ARAMIK SHAHMIRZAIAN
Issued 12/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/18/2025 STEVE MELGAR
Roof/Waste drainage to street Cleared 7/18/2025 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/21/2025 STEVE MELGAR
Sewer availability Cleared 7/21/2025 STEVE MELGAR
GPI Written Notices Cleared 8/12/2025 ARAMIK SHAHMIRZAIAN
Grading Pre-Inspection Cleared 8/12/2025 ARAMIK SHAHMIRZAIAN

Contact Information

Contractor Green Oak Builders; Lic. No.: 929471-B       ,
Engineer Goodman,, Harvey Allan; Lic. No.: C15900 834 17TH STREET      SANTA MONICA, CA 90403

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 6/9/2026   

Inspection Request History

Footing/Foundation/Slab 12/23/2025 Corrections Issued ANTHONY EGSON
Pre-Inspection 12/23/2025 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 1/9/2026 Conditional Approval KIRK SANDERS
Special/Order Compliance 1/9/2026 Corrections Issued KIRK SANDERS
PLUMBING-Rough 1/23/2026 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 1/30/2026 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Partial Approval RYAN SALAZAR
Green Building Rough 4/9/2026 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 4/9/2026 Not Ready for Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 5/7/2026 Conditional Approval ANDREW NAVE
Deputy Wood Construction 5/7/2026 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 5/13/2026 Corrections Issued KIRK SANDERS
HVAC-Rough 5/13/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/14/2026 Approved BOBBY KEY
PLUMBING-Rough 5/14/2026 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 5/19/2026 Partial Approval KIRK SANDERS
HVAC-Rough 5/19/2026 Approved KIRK SANDERS
PLUMBING-Rough 5/19/2026 Approved KIRK SANDERS
Special/Order Compliance 5/19/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/20/2026 Approved KIRK SANDERS
ELECTRICAL-Rough 5/20/2026 Conditional Approval KIRK SANDERS
Green Building Rough 5/20/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 5/20/2026 Partial Approval KIRK SANDERS
Verify Sprinkler Sign Off 5/20/2026 Approved KIRK SANDERS
Insulation 6/1/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 6/4/2026 Approved KIRK SANDERS
Shower Pan 6/4/2026 Approved KIRK SANDERS