1345 1/2 W 218TH ST 90501
Certificate Information: 1345 1/2 W 218TH ST 90501
- Application / Permit
- 25010-10000-02704
- Plan Check / Job No.
- B25LA25125
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU PER LAMC 12.22 A.33(b)(1), NFPA13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Current Status
- Issued on 3/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 7/16/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/24/2025 | TU HUA |
| Assigned to Zoning Architect | 7/24/2025 | RYAN DEL POSO |
| Applicant returned to address corrections | 1/12/2026 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 1/23/2026 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/3/2026 | SERGIO GUTIERREZ |
| Issued | 3/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | XOCHITL ARQUIETA |
| Low Impact Development (LID) | Cleared | 9/25/2025 | MITESH PATEL |
| Sewer availability | Cleared | 10/16/2025 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 10/28/2025 | XOCHITL ARQUIETA |
| Zoning Plan Check | Cleared | 11/25/2025 | RYAN DEL POSO |
Contact Information
| Architect | Tekletsion,, Goitom; Lic. No.: C31925 | 2100 N SEPULVEDA BLVD # 44 MANHATTAN BEACH, CA 90266 |
| Contractor | Alfonso Sanchez; Lic. No.: 921725-B | , |
| Contractor | Sanchez Alfonso; Lic. No.: 921725-B | , |
| Engineer | Gupta,, Raghu; Lic. No.: C87913 | 38725 LEXINGTON ST APT 150 FREMONT, CA 94536 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2026 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/11/2026 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 3/11/2026 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/18/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/19/2026 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/16/2026 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 4/17/2026 | Conditional Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 6/25/2026 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/25/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/25/2026 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/26/2026 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/7/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/13/2026 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/13/2026 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 7/13/2026 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/13/2026 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/17/2026 | Approved | BEN MOLSTAD |