927 N GLENHAVEN DR 90272

Certificate Information: 927 N GLENHAVEN DR 90272

Application / Permit
25010-10000-02672
Plan Check / Job No.
B25LA24871
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, BASEMENT (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/1/2025
Issuing Office
Current Status
Issued on 8/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 KEVIN MORALES
Corrections Issued 6/26/2025 KEVIN MORALES
Quality Review Completed 6/26/2025 EUGENE BARBEAU
Applicant returned to address corrections 7/16/2025 KEVIN MORALES
Plan Check Approved 8/1/2025 KEVIN MORALES
Issued 8/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/30/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/30/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/30/2025 MICHAEL BROWN
Sewer availability Cleared 6/30/2025 MICHAEL BROWN
Low Impact Development (LID) Cleared 7/6/2025 MARTIN FRAGOSO
Hydrant and Access approval Cleared 7/15/2025 JERRY KAO

Contact Information

Architect Makim,, Vaishali Harish; Lic. No.: C29964 2470 COLBY AVENUE      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Insulation 7/21/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/26/2025 Partial Approval TEMISTOCLES CAAL
Piling/Pier/Caisson 8/26/2025 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 8/26/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 8/28/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 8/28/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 9/5/2025 Partial Approval BOBBY KEY
Deputy Shotcrete 9/12/2025 Conditional Approval BOBBY KEY
Reinforced Concrete Frame 9/12/2025 Partial Approval BOBBY KEY
Deputy Shotcrete 9/17/2025 Conditional Approval BOBBY KEY
Deputy Shotcrete 9/24/2025 No Access for Inspection KENNETH NAGLE
Sewer 9/25/2025 Approved STEPHANIE SWANSON
PLUMBING-Rough 10/1/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 10/3/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 10/6/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 10/9/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/9/2025 Approved BOBBY KEY
PLUMBING-Rough 10/9/2025 Partial Approval BOBBY KEY
Deputy Steel/Welding 12/9/2025 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 12/12/2025 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval BOBBY KEY
Underground Mechanical 3/4/2026 Partial Approval BOBBY KEY
HVAC-Rough 4/23/2026 Conditional Approval BOBBY KEY
PLUMBING-Rough 4/23/2026 Corrections Issued BOBBY KEY
Deck 5/1/2026 Approved BOBBY KEY
PLUMBING-Rough 5/1/2026 Not Ready for Inspection BOBBY KEY
Wood Frame 5/1/2026 Approved BOBBY KEY
Deputy Steel/Welding 6/1/2026 Conditional Approval JUAN VALENZUELA
HVAC-Rough 6/1/2026 Approved DANIEL VERA
PLUMBING-Rough 6/1/2026 Approved DANIEL VERA
Interior/Exterior Lathing 6/10/2026 Partial Approval DANIEL VERA
Underground Mechanical 6/10/2026 Approved DANIEL VERA
ELECTRICAL-Rough 6/24/2026 Approved DANIEL VERA
BUILDING-Rough-Frame 6/29/2026 Approved DANIEL VERA
Green Building Rough 6/29/2026 Approved DANIEL VERA
Verify Sprinkler Sign Off 6/29/2026 Approved DANIEL VERA
Wood Frame 6/29/2026 Approved DANIEL VERA