1579 1/2-1/4 E VERNON AVE 90011

Certificate Information: 1579 1/2-1/4 E VERNON AVE 90011

Application / Permit
25010-10000-02666
Plan Check / Job No.
B25LA24802
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED 1-STORY ADU PER STATE LAW AT REAR OF LOT ***13D SPRINKLER*** 2 OF 2
Permit Issued
Issued on 3/18/2026
Issuing Office
Current Status
Issued on 3/18/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 KHUONG TRUONG
Assigned to Zoning Architect 6/20/2025 SARHAD GHEVANDIAN
Corrections Issued 6/24/2025 KHUONG TRUONG
Quality Review Completed 7/3/2025 KEN GILL
Building Plans Picked Up 7/3/2025 APPLICANT
Applicant returned to address corrections 3/9/2026 KHUONG TRUONG
Plan Check Approved 3/11/2026 KHUONG TRUONG
Issued 3/18/2026 APPLICANT

Permit Application Clearance Information

Historic Resource Verification Cleared 7/31/2025 RAFAEL FONTES
Address approval Cleared 8/1/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/1/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 8/1/2025 ROSALINDA MEZA
Roof/Waste drainage to street Cleared 8/1/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/1/2025 BIAINA HARITUNIAN
Frnt yard landscape/Water mgmt Cleared 8/5/2025 ROSALINDA MEZA
Community Plan Implem. Overlay Cleared 8/15/2025 MIGUEL ORNELAS
Community Plan Implem. Overlay Cleared 8/28/2025 COLLINS ALLAN
DAS Clearance Cleared 10/28/2025 KHUONG TRUONG
"D" conditions Cleared 12/2/2025 ANACANY HURTADO
Community Plan Implem. Overlay Cleared 12/2/2025 ANACANY HURTADO
Miscellaneous Cleared 12/2/2025 ANACANY HURTADO
Community Plan Implem. Overlay Cleared 12/3/2025 ENRIQUE ACOSTA
Construction near power lines Cleared 12/3/2025 ENRIQUE ACOSTA
Community Plan Implem. Overlay Cleared 12/12/2025 CINDY QI
Miscellaneous Cleared 12/15/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 12/15/2025 YASMINE BASHIRI
Highway dedication Cleared 1/6/2026 XOCHITL ARQUIETA
Hydrant and Access approval Cleared 1/23/2026 LAVEON RIDER
SB8 RUD Cleared 2/26/2026 JASON WELLS
Zoning Plan Check Cleared 3/2/2026 SARHAD GHEVANDIAN

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2026 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 4/23/2026 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/29/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/29/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/15/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/2/2026 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 6/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/2/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 7/17/2026 Corrections Issued ALEJANDRO DE ARTOLA