520 N SWARTHMORE AVE 90272
Certificate Information: 520 N SWARTHMORE AVE 90272
- Application / Permit
- 25010-10000-02663
- Plan Check / Job No.
- B25LA24781
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/5/2025
- Issuing Office
- Current Status
- Issued on 9/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | JOHNNY WU |
| Corrections Issued | 6/26/2025 | JOHNNY WU |
| Quality Review Completed | 7/8/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/19/2025 | JOHNNY WU |
| Applicant returned to address corrections | 8/27/2025 | JOHNNY WU |
| Applicant returned to address corrections | 8/29/2025 | JOHNNY WU |
| Plan Check Approved | 9/5/2025 | JOHNNY WU |
| Issued | 9/5/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/30/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/30/2025 | MICHAEL BROWN |
| Low Impact Development | Cleared | 8/5/2025 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 8/12/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Willow Group Inc The; Lic. No.: 721043-B | 23974 CRAFTSMAN ROAD CALABASAS, CA 91302 |
| Engineer | Danz,, Joshua; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Richmond, Bryce Dean; Lic. No.: C49628 | 4425 CANOGA AVENUE WOODLAND HILLS, CA 91364 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/8/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/15/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 3/3/2026 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 3/9/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/9/2026 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/11/2026 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/16/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 3/17/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 3/20/2026 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/31/2026 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/31/2026 | Approved | STEPHANIE SWANSON |
| Insulation | 3/31/2026 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/8/2026 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/8/2026 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 4/8/2026 | Approved | STEPHANIE SWANSON |
| Insulation | 4/15/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 4/20/2026 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/21/2026 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 4/22/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/28/2026 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/4/2026 | Approved | STEPHANIE SWANSON |
| Shower Pan | 5/4/2026 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 5/7/2026 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/26/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/4/2026 | Conditional Approval | STEPHANIE SWANSON |