2195 1/2 W 29TH PL 90018
Certificate Information: 2195 1/2 W 29TH PL 90018
- Application / Permit
- 25010-10000-02655
- Plan Check / Job No.
- B25LA24722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ALL-ELECTRIC ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
- Permit Issued
- Issued on 10/9/2025
- Issuing Office
- Current Status
- Issued on 10/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2025 | ISIS ARGUETA |
| Corrections Issued | 6/21/2025 | ISIS ARGUETA |
| Plan Check Approved | 10/7/2025 | GIOVANNY CHAVEZ |
| Issued | 10/9/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | JESSICA OPINION |
| Construction near power lines | Cleared | 8/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/21/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 8/22/2025 | JESSICA OPINION |
| HPOZ | Cleared | 9/25/2025 | DANIEL MATA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Oz General Contractor Inc; Lic. No.: 1093105-B | , |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 12/16/2025 | Conditional Approval | SABAS ALONSO |
| Deputy Methane Barrier | 12/17/2025 | Conditional Approval | SABAS ALONSO |
| Underground Mechanical | 12/17/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 12/30/2025 | Partial Approval | SABAS ALONSO |
| METHANE-Barrier | 12/30/2025 | Corrections Issued | SABAS ALONSO |
| METHANE-Subgrade | 12/30/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Methane Barrier | 1/7/2026 | Conditional Approval | SABAS ALONSO |
| METHANE-Subgrade | 1/9/2026 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 1/12/2026 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 1/14/2026 | Partial Approval | SABAS ALONSO |
| METHANE-Barrier | 1/14/2026 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Methane Barrier | 1/15/2026 | Conditional Approval | SABAS ALONSO |
| Deputy Methane Barrier | 1/16/2026 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 1/21/2026 | Approved | SABAS ALONSO |
| METHANE-Barrier | 1/21/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 2/3/2026 | Not Ready for Inspection | LUIS CASTRO |
| METHANE-Rough | 2/3/2026 | Not Ready for Inspection | LUIS CASTRO |
| Verify Sprinkler Sign Off | 2/3/2026 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/26/2026 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/26/2026 | Corrections Issued | SABAS ALONSO |
| Sewer | 2/26/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/26/2026 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 3/3/2026 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 3/3/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/5/2026 | Conditional Approval | SABAS ALONSO |
| Green Building Final | 3/5/2026 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 3/5/2026 | Approved | SABAS ALONSO |
| METHANE-Rough | 3/5/2026 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 3/5/2026 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 3/10/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/16/2026 | Approved | SABAS ALONSO |
| Shower Pan | 3/18/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/19/2026 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/14/2026 | Conditional Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/14/2026 | Not Ready for Inspection | SABAS ALONSO |