2035-2035 1/2 S PURDUE AVE 90025

Certificate Information: 2035-2035 1/2 S PURDUE AVE 90025

Application / Permit
25010-10000-02653
Plan Check / Job No.
B25LA22977
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
two detached adu
Permit Issued
Issued on 11/18/2025
Issuing Office
Current Status
Issued on 11/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 ARSALAN SHABESTARI
Corrections Issued 6/11/2025 ARSALAN SHABESTARI
Quality Review Completed 6/13/2025 SINA KHOSRAVI
Applicant returned to address corrections 10/26/2025 ARSALAN SHABESTARI
Plan Check Approved 11/16/2025 ARSALAN SHABESTARI
Issued 11/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/24/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/24/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 7/2/2025 PATRICK PEREZ
Low Impact Development (LID) Cleared 7/7/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 7/8/2025 WALLIE JONG
ZA Case Cleared 7/8/2025 CLAUDE GOODING
ZI Cleared 7/8/2025 CLAUDE GOODING
Specific Plan Cleared 8/15/2025 NOAH MCCOY
Specific Plan Cleared 8/27/2025 PEDRO AYALA
Specific Plan Cleared 8/27/2025 PEDRO AYALA
Construction near power lines Cleared 9/17/2025 RIDWAN HARDY
Construction within easement Cleared 9/17/2025 RIDWAN HARDY

Contact Information

Contractor Lida International Building System; Lic. No.: 1064214-B       ,
Contractor Moo Construction; Lic. No.: 1064214-B       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 7/27/2026   

Inspection Request History

Pre-Inspection 2/3/2026 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 2/25/2026 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 3/3/2026 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 3/3/2026 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 3/13/2026 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 3/13/2026 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Partial Approval MICHAEL ALLEN
Sewer 3/31/2026 Approved ANDREW NAVE
Deputy Wood Construction 4/15/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Partial Approval MICHAEL ALLEN
Wood Frame 5/6/2026 Partial Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Corrections Issued MICHAEL LEWIS
Wood Frame 5/7/2026 Corrections Issued MICHAEL LEWIS
Wood Frame 5/8/2026 Not Ready for Inspection ANTHONY EGSON
Deputy Wood Construction 6/5/2026 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/29/2026 Not Ready for Inspection ANTHONY EGSON