5033 S DENKER AVE 90062

Certificate Information: 5033 S DENKER AVE 90062

Application / Permit
25010-10000-02616
Plan Check / Job No.
B25LA24188
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, ALL ELECTRIC 26'-0"X34'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2025 APPLICANT
Assigned to Plan Check Engineer 6/20/2025 KAMYAR EMAMI
Corrections Issued 6/23/2025 KAMYAR EMAMI
Applicant returned to address corrections 7/10/2025 MADISON ODELL
Applicant returned to address corrections 7/30/2025 MADISON ODELL
Applicant returned to address corrections 8/2/2025 KAMYAR EMAMI
Plan Check Approved 8/7/2025 MOHAMMAD ESMAILI
No Progress 8/13/2025 MOHAMMAD ESMAILI
Plan Check Approved 8/13/2025 MOHAMMAD ESMAILI
Issued 8/13/2025 APPLICANT
CofO in Progress 4/10/2026 SABAS ALONSO
Permit Finaled 4/11/2026 DEROLD HAUFF
CofO Issued 4/11/2026 DEROLD HAUFF
Permit Finaled 4/11/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/9/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/9/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/14/2025 TAL SHEMEN
Sewer availability Cleared 7/14/2025 TAL SHEMEN

Contact Information

Architect Resendiz,, Alejandro; Lic. No.: NA11660       ,
Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2025 Corrections Issued SABAS ALONSO
Sewer 10/28/2025 Approved SABAS ALONSO
Underground Mechanical 10/28/2025 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/31/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 11/7/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/25/2025 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/25/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 12/2/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/10/2025 Corrections Issued SABAS ALONSO
Green Building Rough 12/10/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 12/10/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 12/10/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/12/2025 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 12/12/2025 Approved SCOTT FINNILA
HVAC-Rough 12/15/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 12/17/2025 Approved SABAS ALONSO
HVAC-Rough 12/17/2025 Approved SABAS ALONSO
Insulation 12/18/2025 Corrections Issued SABAS ALONSO
Drywall Nailing 12/22/2025 Approved DEVON JACKSON
Shower Pan 12/22/2025 Approved DEVON JACKSON
Insulation 12/24/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 12/24/2025 Approved SABAS ALONSO
Underground Mechanical 12/31/2025 Approved SABAS ALONSO
Final 1/22/2026 Corrections Issued SABAS ALONSO
Green Building Final 1/22/2026 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Not Ready SABAS ALONSO
Service/Power Release 1/22/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/22/2026 Approved SABAS ALONSO
Final 1/27/2026 Corrections Issued SABAS ALONSO
Green Building Final 1/27/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/27/2026 Approved SABAS ALONSO
Final 4/6/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 4/6/2026 Approved SABAS ALONSO