2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 10/18/2025
Issuing Office
Current Status
Issued on 10/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/2/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 HERNAN ARREOLA
Corrections Issued 7/14/2025 HERNAN ARREOLA
Quality Review Completed 7/14/2025 CHAD DOI
Applicant returned to address corrections 7/31/2025 HERNAN ARREOLA
Applicant returned to address corrections 9/4/2025 HERNAN ARREOLA
Plan Check Approved 10/17/2025 HERNAN ARREOLA
Issued 10/18/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 8/19/2025 RIDWAN HARDY
Hydrant and Access approval Cleared 9/10/2025 GILBERT URREA

Contact Information

Contractor Classical Progression Inc; Lic. No.: 823135-B 128 WADSWORTH AVE      SANTA MONICA, CA 90405

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/19/2025 Partial Approval BOBBY KEY
Sewer 12/19/2025 Not Ready for Inspection BOBBY KEY
Deputy Reinf. Concrete 2/6/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval BOBBY KEY
Footing/Foundation/Slab 2/9/2026 Partial Approval BOBBY KEY
Deputy Reinf. Concrete 2/13/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/5/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Corrections Issued BOBBY KEY
Deputy Wood Construction 4/23/2026 Conditional Approval JUAN VALENZUELA