900 N LACHMAN LANE 90272
Certificate Information: 900 N LACHMAN LANE 90272
- Application / Permit
- 25010-10000-02594
- Plan Check / Job No.
- B25LA23958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY 81'-11" x 57'-9" 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | KEVIN MORALES |
| Corrections Issued | 6/24/2025 | KEVIN MORALES |
| Quality Review Completed | 6/24/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/15/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 7/25/2025 | KEVIN MORALES |
| Plan Check Approved | 8/8/2025 | KEVIN MORALES |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2025 | CELINA MORENO |
| Sewer availability | Cleared | 6/25/2025 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 6/27/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/30/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 7/2/2025 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tsao,, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 562 31ST ST MANHATTAN BEACH, CA 90266 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2025 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/1/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/31/2025 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 12/31/2025 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 1/5/2026 | Partial Approval | BOBBY KEY |
| Wood Frame | 1/5/2026 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2026 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 1/6/2026 | Partial Approval | DANIEL VERA |
| Deputy Wood Construction | 1/20/2026 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 1/23/2026 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/10/2026 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 3/26/2026 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 3/26/2026 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Approved | BOBBY KEY |
| Green Building Rough | 3/26/2026 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 3/26/2026 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 3/26/2026 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 3/26/2026 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/7/2026 | Approved | BOBBY KEY |
| HVAC-Rough | 4/7/2026 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 6/5/2026 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 7/6/2026 | Approved | DANIEL VERA |
| Insulation | 7/6/2026 | Corrections Issued | DANIEL VERA |
| Drywall Nailing | 7/14/2026 | Approved | ARAM AVEDISIAN |
| Insulation | 7/14/2026 | Approved | ARAM AVEDISIAN |