935 N AMALFI DR 90272
Certificate Information: 935 N AMALFI DR 90272
- Application / Permit
- 25010-10000-02548
- Plan Check / Job No.
- B25LA23561
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | ALEXANDER JOO |
| Corrections Issued | 6/14/2025 | ALEXANDER JOO |
| Quality Review Completed | 6/20/2025 | KEN GILL |
| Building Plans Picked Up | 6/26/2025 | APPLICANT |
| Applicant returned to address corrections | 7/24/2025 | ALEXANDER JOO |
| Plan Check Approved | 8/14/2025 | ALEXANDER JOO |
| Plan Check Approved | 8/14/2025 | MARILYN SEVILLA |
| Issued | 8/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 6/25/2025 | JESUS CISNEROS |
| Address approval | Cleared | 6/30/2025 | JESUS CISNEROS |
| Hydrant and Access approval | Cleared | 7/1/2025 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 7/23/2025 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 7/24/2025 | JOHNNY MIRANDA |
| Grading Pre-Inspection | Cleared | 7/24/2025 | JOHNNY MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/15/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/22/2025 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 8/22/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Footing/Foundation/Slab | 8/25/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 9/10/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 12/3/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 12/3/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 12/3/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/5/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/11/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Approved | HERBERT GIRON |
| Green Building Rough | 12/11/2025 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 12/11/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/19/2025 | Approved | HERBERT GIRON |
| Shower Pan | 12/19/2025 | Partial Approval | HERBERT GIRON |
| Insulation | 1/13/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 1/23/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/8/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 6/8/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/8/2026 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 6/8/2026 | Approved | HERBERT GIRON |