3146 W ATWATER AVE 90039

Certificate Information: 3146 W ATWATER AVE 90039

Application / Permit
25010-10000-02535
Plan Check / Job No.
B25LA23429
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New Detached 1-Story ADU per GC 66323(a)(2)
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2025 APPLICANT
Assigned to Plan Check Engineer 6/10/2025 DAVID CASTILLO
Corrections Issued 6/11/2025 DAVID CASTILLO
Applicant returned to address corrections 7/3/2025 ALFREDO JARA
Plan Check Approved 7/14/2025 ALFREDO JARA
Issued 7/28/2025 APPLICANT
CofO in Progress 4/27/2026 NICHOLAS LOPEZ
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/24/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/24/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/27/2025 SAFA JAVANMARDI
Construction near power lines Cleared 7/9/2025 WALTER RAMIREZ

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/1/2025 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 8/15/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Corrections Issued NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 9/10/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 11/4/2025 Approved NICHOLAS LOPEZ
Green Building Rough 11/4/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 11/4/2025 Partial Approval NICHOLAS LOPEZ
Verify Sprinkler Sign Off 11/4/2025 Approved NICHOLAS LOPEZ
Insulation 11/14/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 11/18/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 12/23/2025 Partial Approval NICHOLAS LOPEZ
Shower Pan 12/24/2025 Approved NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 2/26/2026 Approved NICHOLAS LOPEZ
Sewer 4/13/2026 Approved NICHOLAS LOPEZ
Final 4/22/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 4/22/2026 Approved NICHOLAS LOPEZ
Green Building Final 4/22/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 4/22/2026 Not Required NICHOLAS LOPEZ
Smoke Detectors 4/22/2026 Approved NICHOLAS LOPEZ
Final 4/24/2026 OK to Issue CofO NICHOLAS LOPEZ