3146 W ATWATER AVE 90039
Certificate Information: 3146 W ATWATER AVE 90039
- Application / Permit
- 25010-10000-02535
- Plan Check / Job No.
- B25LA23429
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New Detached 1-Story ADU per GC 66323(a)(2)
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2025 | DAVID CASTILLO |
| Corrections Issued | 6/11/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/3/2025 | ALFREDO JARA |
| Plan Check Approved | 7/14/2025 | ALFREDO JARA |
| Issued | 7/28/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/24/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/27/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 7/9/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/1/2025 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 11/4/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 11/4/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 11/4/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 11/18/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 12/23/2025 | Partial Approval | NICHOLAS LOPEZ |
| Shower Pan | 12/24/2025 | Approved | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/26/2026 | Approved | NICHOLAS LOPEZ |
| Sewer | 4/13/2026 | Approved | NICHOLAS LOPEZ |
| Final | 4/22/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 4/22/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 4/22/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 4/22/2026 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 4/22/2026 | Approved | NICHOLAS LOPEZ |
| Final | 4/24/2026 | OK to Issue CofO | NICHOLAS LOPEZ |