16811 W EDGAR ST 90272

Certificate Information: 16811 W EDGAR ST 90272

Application / Permit
25010-10000-02530
Plan Check / Job No.
B25LA23368
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING (2)-STORY 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/15/2025
Issuing Office
Current Status
Issued on 8/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/5/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 VU NGUYEN
Corrections Issued 6/10/2025 VU NGUYEN
Quality Review Completed 6/10/2025 EUGENE BARBEAU
Applicant returned to address corrections 7/14/2025 VU NGUYEN
Applicant returned to address corrections 7/18/2025 VU NGUYEN
Plan Check Approved 8/15/2025 VU NGUYEN
Issued 8/15/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/12/2025 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 6/12/2025 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 6/12/2025 VLADIMIR ARUTYUNYAN
Hydrant and Access approval Cleared 7/10/2025 JOHN CONNEALLY
Green Code Cleared 8/8/2025 MICHAEL MARTINEZ

Contact Information

Contractor Deep Canyon Design + Build Corporation; Lic. No.: 1135670-B 1447 FERNWOOD PACIFIC      TOPANGA CANYON, CA 90290
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2025 Not Ready for Inspection BOBBY KEY
Pre-Inspection 8/22/2025 Partial Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 9/23/2025 Conditional Approval MEL KHACHATOURIAN
PLUMBING-Rough 9/23/2025 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 9/25/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/14/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 3/3/2026 Not Ready for Inspection DANIEL VERA
HVAC-Rough 3/3/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 3/3/2026 Not Ready for Inspection DANIEL VERA
Wood Frame 3/3/2026 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 3/5/2026 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/5/2026 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Corrections Issued BOBBY KEY
HVAC-Rough 3/5/2026 Corrections Issued BOBBY KEY
PLUMBING-Rough 3/5/2026 Partial Approval BOBBY KEY
ELECTRICAL-Rough 3/24/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval BOBBY KEY
HVAC-Rough 3/24/2026 Approved BOBBY KEY
Interior/Exterior Lathing 3/24/2026 Partial Approval BOBBY KEY
PLUMBING-Rough 3/24/2026 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 4/23/2026 Approved BOBBY KEY
Green Building Rough 4/23/2026 Approved BOBBY KEY
Verify Sprinkler Sign Off 4/23/2026 Approved BOBBY KEY
Insulation 5/5/2026 Corrections Issued DANIEL VERA
Drywall Nailing 5/21/2026 Approved MICHAEL ALLEN
Insulation 5/21/2026 Approved MICHAEL ALLEN