1422 W HEPNER AVE 90041
Certificate Information: 1422 W HEPNER AVE 90041
- Application / Permit
- 25010-10000-02524
- Plan Check / Job No.
- B25LA23296
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW 30'-0" X 20'-0", 1,200 S.F., TWO STORY ADU PERLAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Current Status
- CofO Issued on 3/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | VARAND SARKISIAN |
| Corrections Issued | 6/17/2025 | VARAND SARKISIAN |
| Quality Review Completed | 6/24/2025 | GARO TELMI |
| Plan Check Approved | 7/9/2025 | VARAND SARKISIAN |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 3/4/2026 | RONNIE MEDINA |
| Permit Finaled | 3/4/2026 | DEROLD HAUFF |
| Permit Finaled | 3/4/2026 | DEROLD HAUFF |
| CofO Issued | 3/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/1/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/1/2025 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 7/9/2025 | VARAND SARKISIAN |
Contact Information
| Architect | Olmos,, Bertha A; Lic. No.: C35995 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/21/2025 | Partial Approval | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/26/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| ELECTRICAL-Rough | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| HVAC-Rough | 10/15/2025 | Approved | RONNIE MEDINA |
| PLUMBING-Rough | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Wood Frame | 10/15/2025 | Not Ready for Inspection | RONNIE MEDINA |
| BUILDING-Rough-Frame | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| ELECTRICAL-Rough | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Green Building Rough | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| HVAC-Rough | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Rough | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 10/21/2025 | Approved | RONNIE MEDINA |
| Wood Frame | 10/21/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | RONNIE MEDINA |
| Rough-Elec/Plmb/HVAC | 10/23/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 10/28/2025 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Partial Inspection | RONNIE MEDINA |
| Green Building Rough | 10/28/2025 | Approved | RONNIE MEDINA |
| Insulation | 10/29/2025 | Corrections Issued | REGINA MENDEZ |
| Interior/Exterior Lathing | 10/29/2025 | Approved | REGINA MENDEZ |
| Insulation | 11/4/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 11/10/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 11/10/2025 | Partial Approval | RONNIE MEDINA |
| Underground Mechanical | 11/17/2025 | Partial Approval | RONNIE MEDINA |
| Underground Mechanical | 11/19/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 12/4/2025 | No Access for Inspection | RONNIE MEDINA |
| Shower Pan | 12/4/2025 | No Access for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 12/8/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 12/8/2025 | Approved | GEM DE OCAMPO |
| ELECTRICAL-Final | 2/25/2026 | Approved | RONNIE MEDINA |
| Final | 2/25/2026 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 2/25/2026 | Approved | RONNIE MEDINA |
| HVAC-Final | 2/25/2026 | Approved | RONNIE MEDINA |
| PLUMBING-Final | 2/25/2026 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | RONNIE MEDINA |
| Service/Power Release | 2/25/2026 | Approved | RONNIE MEDINA |
| Smoke Detectors | 2/25/2026 | Approved | RONNIE MEDINA |
| Final | 3/4/2026 | OK to Issue CofO | RONNIE MEDINA |