1242 1/2 S STANLEY AVE 90019
Certificate Information: 1242 1/2 S STANLEY AVE 90019
- Application / Permit
- 25010-10000-02521
- Plan Check / Job No.
- B25LA23240
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE (N) 798 SQ FT ADU PER GC 66323(a)(2)
- Permit Issued
- Issued on 7/30/2025
- Issuing Office
- Current Status
- Issued on 7/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | VARAND SARKISIAN |
| Corrections Issued | 6/17/2025 | VARAND SARKISIAN |
| Quality Review Completed | 6/25/2025 | GARO TELMI |
| Plan Check Approved | 7/30/2025 | VARAND SARKISIAN |
| Issued | 7/30/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/3/2025 | WALTER RAMIREZ |
| Address approval | Cleared | 7/7/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2025 | JEANIE LAM |
| Sewer availability | Cleared | 7/8/2025 | JEANIE LAM |
Contact Information
| Contractor | Axe Construction Inc; Lic. No.: 1069232-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: NA93320 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/9/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 9/9/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 9/11/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 9/30/2025 | Approved | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 10/6/2025 | Approved | ARTHUR NEGRETE |
| Deputy Methane Barrier | 10/15/2025 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 10/17/2025 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 10/17/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Subgrade | 10/17/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 11/7/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Corrections Issued | JUSTIN HAWLEY |
| Deputy Wood Construction | 12/4/2025 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/16/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/26/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/26/2026 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 1/26/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/5/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 2/5/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 2/5/2026 | Corrections Issued | BRENDAN MORELLI |
| Wood Frame | 2/5/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 2/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 2/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Special/Order Compliance | 2/9/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/10/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 2/10/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/10/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 2/10/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/2/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 3/2/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Rough | 3/2/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 3/2/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/3/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/3/2026 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 3/3/2026 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 3/3/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/9/2026 | Conditional Approval | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | WILLIAM SIERRA |
| Insulation | 3/10/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | GEM DE OCAMPO |
| Insulation | 3/12/2026 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 3/12/2026 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 3/16/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 3/16/2026 | Approved | RONNIE MINDANAO |
| Shower Pan | 3/16/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 3/18/2026 | Not Ready for Inspection | JOSH MEISTER |
| Drywall Nailing | 3/20/2026 | Approved | JUSTIN HAWLEY |