14917 W DRUMMOND ST 90272
Certificate Information: 14917 W DRUMMOND ST 90272
- Application / Permit
- 25010-10000-02510
- Plan Check / Job No.
- B25LA23097
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Current Status
- Issued on 7/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2025 | STARR CHEN |
| Corrections Issued | 6/11/2025 | STARR CHEN |
| Quality Review Completed | 6/11/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/3/2025 | STARR CHEN |
| Plan Check Approved | 7/17/2025 | STARR CHEN |
| Issued | 7/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2025 | DAVID PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | DAVID PEREZ |
| Permit | Cleared | 6/13/2025 | DAVID PEREZ |
| Sewer availability | Cleared | 6/13/2025 | DAVID PEREZ |
| Low Impact Development (LID) | Cleared | 6/27/2025 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 7/1/2025 | PATRICK PEREZ |
| Trees in Parkway | Cleared | 7/10/2025 | RICHARD SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
Contact Information
| Architect | , ; Lic. No.: C34990 | 2347 OCEAN AVE VENICE, CA 90291 |
| Contractor | Arttcon Inc; Lic. No.: 1138192-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 9/2/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/4/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/16/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/30/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/5/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/13/2026 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/10/2026 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 4/10/2026 | Conditional Approval | DANIEL VERA |
| PLUMBING-Rough | 4/10/2026 | Not Ready for Inspection | DANIEL VERA |
| Pre-Inspection | 4/10/2026 | Partial Inspection | DANIEL VERA |
| PLUMBING-Rough | 4/13/2026 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/15/2026 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/29/2026 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/29/2026 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 4/29/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | STEPHANIE SWANSON |