6115 S VERDUN AVE 90043

Certificate Information: 6115 S VERDUN AVE 90043

Application / Permit
25010-10000-02461
Plan Check / Job No.
B25LA22647
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - NEW 1 STORY ADU WITH ATTACHED RAISED DECK PER GC 66323(a)(2)
Permit Issued
Issued on 9/4/2025
Issuing Office
Current Status
Issued on 9/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 STARR CHEN
Corrections Issued 6/17/2025 STARR CHEN
Quality Review Completed 6/18/2025 KEVIN MORALES
Applicant returned to address corrections 7/11/2025 STARR CHEN
Applicant returned to address corrections 7/24/2025 STARR CHEN
Plan Check Approved 9/3/2025 STARR CHEN
Issued 9/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/7/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 7/7/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/7/2025 DERRICK MAGEE
Sewer availability Cleared 7/7/2025 DERRICK MAGEE
Grading Pre-Inspection Cleared 7/8/2025 RUSSELL BONVOULOIR
Hydrant and Access approval Cleared 7/16/2025 GILBERT URREA
GPI Written Notices Cleared 8/15/2025 STARR CHEN
Construction near power lines Cleared 8/28/2025 ENRIQUE ACOSTA

Contact Information

Contractor The K & L Corporation; Lic. No.: 1119795-B       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/11/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 9/11/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 9/11/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 10/1/2025 Partial Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 10/1/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/5/2025 Approved BOBBY KEY
Footing/Foundation/Slab 12/5/2025 Approved BOBBY KEY
BUILDING-Rough-Frame 12/29/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 12/29/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/6/2026 Conditional Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Conditional Approval MICHAEL LEWIS
PLUMBING-Rough 1/28/2026 Approved MICHAEL LEWIS
ELECTRICAL-Rough 3/17/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 3/17/2026 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 3/17/2026 Partial Approval SALVADOR MARTINEZ
Shower Pan 3/17/2026 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/24/2026 Approved ALEX COLIN
ELECTRICAL-Rough 4/16/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 4/16/2026 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/20/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 4/20/2026 Conditional Approval SALVADOR MARTINEZ
Green Building Rough 4/20/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 4/20/2026 Approved SALVADOR MARTINEZ
Verify Sprinkler Sign Off 4/20/2026 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/21/2026 Conditional Approval SALVADOR MARTINEZ
Green Building Rough 5/21/2026 Approved SALVADOR MARTINEZ
Order to Comply 5/21/2026 Not Required SALVADOR MARTINEZ
Insulation 6/3/2026 Conditional Approval ALEX COLIN