839 N GALLOWAY ST 90272
Certificate Information: 839 N GALLOWAY ST 90272
- Application / Permit
- 25010-10000-02446
- Plan Check / Job No.
- B25LA22582
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY 13D SPRINKLERS THROUGHOUT SOLAR INSTALLATION EXEMPT PER GOVERNER'S EO N-29-25
- Permit Issued
- Issued on 8/4/2025
- Issuing Office
- Current Status
- Issued on 8/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | VIVIAN LAO |
| Corrections Issued | 6/13/2025 | VIVIAN LAO |
| Quality Review Completed | 6/13/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 7/7/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 7/30/2025 | VIVIAN LAO |
| Plan Check Approved | 7/31/2025 | VIVIAN LAO |
| Issued | 8/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/18/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 7/21/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Shirley Construction Co; Lic. No.: 602138-B | , |
| Contractor | Shirley David M Construction Corporation; Lic. No.: 602138-B | , |
| Engineer | Shirley,, Peter; Lic. No.: NA75050 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/25/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/9/2025 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 9/25/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/21/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/26/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | BOBBY KEY |
| Green Building Rough | 1/30/2026 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/30/2026 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 1/30/2026 | Approved | BOBBY KEY |
| Insulation | 2/17/2026 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/13/2026 | Approved | DANIEL VERA |