1542 W 215TH ST 90501

Certificate Information: 1542 W 215TH ST 90501

Application / Permit
25010-10000-02433
Plan Check / Job No.
B25LA22520
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 21' X 35'-7" DETACHED ADU PER STATE LAW (GCS 66323(a)(2)) WITH ATTACHED OPEN TRELLIS ( 8'-0" X 24'-00").
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
CofO Issued on 1/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 LAWRENCE QUIRANTE
Corrections Issued 6/7/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 6/12/2025 APPLICANT
Plan Check Approved 6/26/2025 CRISTINA SALAZAR
Issued 7/1/2025 APPLICANT
CofO in Progress 11/25/2025 EUGENE CASSIDY
Permit Finaled 1/23/2026 ANSON MAGLASANG
CofO Issued 1/23/2026 ANSON MAGLASANG
Permit Finaled 1/23/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/5/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 6/5/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 6/10/2025 CINDY QI
Sewer availability Cleared 6/10/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/7/2025 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/18/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 7/18/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/22/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/7/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/7/2025 Approved EUGENE CASSIDY
Green Building Rough 8/7/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 8/7/2025 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 8/7/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/7/2025 Approved EUGENE CASSIDY
Insulation 8/11/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/11/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 8/13/2025 Approved EUGENE CASSIDY
Final 10/21/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 10/21/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 10/21/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/21/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/31/2025 Approved EUGENE CASSIDY
Final 10/31/2025 OK to Issue CofO EUGENE CASSIDY
Green Building Final 10/31/2025 Approved EUGENE CASSIDY
HVAC-Final 10/31/2025 Approved EUGENE CASSIDY
PLUMBING-Final 10/31/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/31/2025 Not Ready for Inspection EUGENE CASSIDY