1122 N CHARM ACRES PL 90272

Certificate Information: 1122 N CHARM ACRES PL 90272

Application / Permit
25010-10000-02385
Plan Check / Job No.
B25LA22098
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 52' X 55'-2". NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
Issued on 11/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/2/2025 RAPHAEL ROSAS
Corrections Issued 6/4/2025 RAPHAEL ROSAS
Quality Review Completed 6/6/2025 STEVEN KIM
Applicant returned to address corrections 9/17/2025 RAPHAEL ROSAS
Plan Check Approved 10/23/2025 RAPHAEL ROSAS
Issued 11/12/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/16/2025 DAVID LOPEZ
Sewer availability Cleared 6/16/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 6/26/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265
Engineer Nazari,, Arthur; Lic. No.: NA53497       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 6/11/2026    Time Frame: 2-4

Inspection Request History

PLUMBING-Rough 12/12/2025 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 12/17/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 12/17/2025 Approved TEMISTOCLES CAAL
Deputy Wood Construction 1/14/2026 Conditional Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 5/19/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 5/22/2026 Approved EVAN COOPER
PLUMBING-Rough 5/22/2026 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Approved JESUS PINEDA
Green Building Rough 5/26/2026 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 5/26/2026 Approved JESUS PINEDA
Deputy Wood Construction 5/27/2026 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/1/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Approved TEMISTOCLES CAAL
Green Building Rough 6/1/2026 Approved TEMISTOCLES CAAL
PLUMBING-Rough 6/1/2026 Partial Approval TEMISTOCLES CAAL
Insulation 6/8/2026 Approved TEMISTOCLES CAAL