840 N EDGEMONT ST 90029

Certificate Information: 840 N EDGEMONT ST 90029

Application / Permit
25010-10000-02368
Plan Check / Job No.
B25LA21926
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW DETACHED ACCESSORY DWELLING UNIR PER GC66323(a)(2). ALL WORK PER ENGINEER.
Permit Issued
Issued on 11/5/2025
Issuing Office
Current Status
Issued on 11/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/2/2025 NAREG ATARIAN
Corrections Issued 6/3/2025 NAREG ATARIAN
Applicant returned to address corrections 8/1/2025 NAREG ATARIAN
Applicant returned to address corrections 8/6/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 8/28/2025 NAREG ATARIAN
Issued 11/5/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/13/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/13/2025 MICHAEL BROWN
Construction near power lines Cleared 7/30/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/31/2025 MICHAEL BROWN
Sewer availability Cleared 7/31/2025 MICHAEL BROWN

Contact Information

Contractor Buildoly Inc; Lic. No.: 1134744-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2025 Approved FREDDIE RIVERA
Pre-Inspection 11/26/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 12/5/2025 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/10/2025 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 12/17/2025 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 12/19/2025 Partial Inspection ANTHONY RAMOS
Sewer 12/19/2025 Approved ANTHONY RAMOS
Underground Mechanical 12/19/2025 Approved ANTHONY RAMOS
ELECTRICAL-Rough 2/3/2026 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved FREDDIE RIVERA
PLUMBING-Rough 2/3/2026 Corrections Issued FREDDIE RIVERA
HVAC-Rough 2/10/2026 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 2/10/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/3/2026 Approved FREDDIE RIVERA
HVAC-Rough 3/11/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/12/2026 Corrections Issued FREDDIE RIVERA
Green Building Rough 3/12/2026 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/12/2026 Approved FREDDIE RIVERA
Insulation 3/24/2026 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 3/25/2026 Approved FREDDIE RIVERA
Drywall Nailing 4/1/2026 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/9/2026 Approved FREDDIE RIVERA
Final 6/3/2026 Corrections Issued FREDDIE RIVERA
Green Building Final 6/3/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 6/3/2026 Approved FREDDIE RIVERA
Smoke Detectors 6/3/2026 Approved FREDDIE RIVERA