840 N EDGEMONT ST 90029
Certificate Information: 840 N EDGEMONT ST 90029
- Application / Permit
- 25010-10000-02368
- Plan Check / Job No.
- B25LA21926
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW DETACHED ACCESSORY DWELLING UNIR PER GC66323(a)(2). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 11/5/2025
- Issuing Office
- Current Status
- Issued on 11/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | NAREG ATARIAN |
| Corrections Issued | 6/3/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/1/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/6/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/28/2025 | NAREG ATARIAN |
| Issued | 11/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/13/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 7/30/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/31/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Buildoly Inc; Lic. No.: 1134744-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2025 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 11/26/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 12/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 12/10/2025 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/19/2025 | Partial Inspection | ANTHONY RAMOS |
| Sewer | 12/19/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 12/19/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Rough | 2/3/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/3/2026 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 2/10/2026 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 2/10/2026 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/3/2026 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 3/11/2026 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/12/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 3/12/2026 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/12/2026 | Approved | FREDDIE RIVERA |
| Insulation | 3/24/2026 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/1/2026 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/9/2026 | Approved | FREDDIE RIVERA |
| Final | 6/3/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/3/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 6/3/2026 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/3/2026 | Approved | FREDDIE RIVERA |