3007 W 67TH ST 90043
Certificate Information: 3007 W 67TH ST 90043
- Application / Permit
- 25010-10000-02319
- Plan Check / Job No.
- B25LA21597
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per GC 66323(a)(2)
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2025 | SHANGQIN XIE |
| Corrections Issued | 6/2/2025 | SHANGQIN XIE |
| Plan Check Approved | 6/10/2025 | SHANGQIN XIE |
| Issued | 6/24/2025 | APPLICANT |
| CofO in Progress | 10/22/2025 | SALVADOR MARTINEZ |
| No Progress | 10/26/2025 | DEROLD HAUFF |
| CofO in Progress | 10/26/2025 | DEROLD HAUFF |
| Permit Finaled | 10/27/2025 | DEROLD HAUFF |
| CofO Issued | 10/27/2025 | DEROLD HAUFF |
| Permit Finaled | 10/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 6/6/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 6/6/2025 | JESSICA OPINION |
Contact Information
| Contractor | Don Construction; Lic. No.: 840108-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/14/2025 | Approved | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 7/16/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/16/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Corrections Issued | WAYNE REGESTER |
| Wood Frame | 8/1/2025 | Partial Approval | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/5/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 8/5/2025 | Partial Approval | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 8/5/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 8/5/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 8/20/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 8/20/2025 | Partial Approval | WAYNE REGESTER |
| Rough-Elec/Plmb/HVAC | 8/20/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 8/20/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Deputy Drilled-In Anchors | 8/21/2025 | Approved | WAYNE REGESTER |
| Insulation | 8/22/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 8/28/2025 | Approved | ANTHONY RAMOS |
| Gas Test | 8/28/2025 | Approved | ANTHONY RAMOS |
| Service/Power Release | 9/17/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 9/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 9/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 10/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 10/1/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 10/1/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 10/1/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 10/6/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 10/6/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/8/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 10/8/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Final | 10/21/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 10/21/2025 | Approved | SALVADOR MARTINEZ |