12817 W NEWTON ST 91342

Certificate Information: 12817 W NEWTON ST 91342

Application / Permit
25010-10000-02288
Plan Check / Job No.
B25LA21404
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
N DETACHED 1 STORY ADU Per GC 66323(A)(2)
Permit Issued
Issued on 2/5/2026
Issuing Office
Valley
Current Status
Issued on 2/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 JESSE VIDUYA
Corrections Issued 6/24/2025 JESSE VIDUYA
Quality Review Completed 6/30/2025 KEN GILL
Building Plans Picked Up 7/9/2025 APPLICANT
Plan Check Approved 9/30/2025 JESSE VIDUYA
Issued 2/5/2026 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 7/26/2025 ENRIQUE ACOSTA
Hydrant and Access approval Cleared 9/9/2025 FRANK GOMEZ
Address approval Cleared 9/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/22/2025 BIAINA HARITUNIAN
GPI Written Notices Cleared 9/30/2025 JESSE VIDUYA
Grading Pre-Inspection Cleared 9/30/2025 JESSE VIDUYA

Contact Information

Contractor Ecorise Construction And Remodeling; Lic. No.: 1126591-B 5833 YARMOUTH AVE      ENCINO, CA 91316
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/12/2026 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 2/24/2026 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 2/26/2026 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/24/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 3/24/2026 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 3/24/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 3/24/2026 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 3/24/2026 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 3/24/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 3/26/2026 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval KEVIN BERBERYAN
HVAC-Rough 3/26/2026 Approved KEVIN BERBERYAN
PLUMBING-Rough 3/26/2026 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 3/26/2026 Approved KEVIN BERBERYAN
Sewer 3/26/2026 Approved KEVIN BERBERYAN
Wood Frame 3/26/2026 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/3/2026 Approved KEVIN BERBERYAN
Shower Pan 4/3/2026 Approved KEVIN BERBERYAN
Insulation 4/9/2026 Approved JOSE AVILA
Drywall Nailing 4/15/2026 Approved KEVIN BERBERYAN
Green Building Rough 4/15/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/20/2026 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 4/30/2026 Approved MISAEL ESPARZA