3623 S GREENWOOD AVE 90066

Certificate Information: 3623 S GREENWOOD AVE 90066

Application / Permit
25010-10000-02282
Plan Check / Job No.
B25LA21314
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(2). To be sprinklered thru-out with NFPA-13D sprinklers. 2 OF 2
Permit Issued
Issued on 8/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 5/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 MICHAEL LOPEZ
Assigned to Zoning Architect 5/29/2025 KRISTEL MARQUEZ
Corrections Issued 6/5/2025 MICHAEL LOPEZ
Quality Review Completed 6/6/2025 KEN GILL
Building Plans Picked Up 6/10/2025 APPLICANT
Plan Check Approved 8/5/2025 MATTHEW TORRES
Issued 8/6/2025 APPLICANT
CofO in Progress 5/19/2026 DAKOTA LOW
Permit Finaled 5/20/2026 RICHARD STEINBACH
CofO Issued 5/20/2026 RICHARD STEINBACH
Permit Finaled 5/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/12/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/12/2025 MICHAEL BROWN
Low Impact Development (LID) Cleared 6/12/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 6/12/2025 MICHAEL BROWN
Sewer availability Cleared 6/12/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 6/25/2025 JOHN CONNEALLY
Grading Pre-Inspection Cleared 6/30/2025 MICHAEL TEMPLE
Specific Plan Cleared 7/10/2025 EDER ROMERO
Zoning Plan Check Cleared 7/15/2025 KRISTEL MARQUEZ
GPI Written Notices Cleared 8/5/2025 MICHAEL LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/6/2025 Partial Approval WILBER ROSALES
Footing/Foundation/Slab 10/6/2025 Partial Approval WILBER ROSALES
Underground Mechanical 10/6/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 10/20/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 11/12/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 11/12/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved WILBER ROSALES
Green Building Rough 11/12/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Rough 11/12/2025 Approved WILBER ROSALES
PLUMBING-Rough 11/12/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 11/12/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 11/20/2025 Approved WILBER ROSALES
Green Building Rough 11/20/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 11/20/2025 Partial Approval WILBER ROSALES
Verify Sprinkler Sign Off 11/20/2025 Approved WILBER ROSALES
Insulation 12/1/2025 Approved KENNETH NAGLE
Shower Pan 12/1/2025 Approved KENNETH NAGLE
Drywall Nailing 12/5/2025 Approved WILBER ROSALES
ELECTRICAL-Final 4/14/2026 Corrections Issued DAKOTA LOW
Gas Test 4/14/2026 Not Ready for Inspection DAKOTA LOW
HVAC-Final 4/14/2026 Corrections Issued DAKOTA LOW
PLUMBING-Final 4/14/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Final 4/30/2026 Approved DAKOTA LOW
Gas Test 4/30/2026 Approved DAKOTA LOW
PLUMBING-Final 4/30/2026 Corrections Issued DAKOTA LOW
Smoke Detectors 4/30/2026 Approved DAKOTA LOW
Final 5/6/2026 Corrections Issued DAKOTA LOW
Green Building Final 5/6/2026 Approved DAKOTA LOW
HVAC-Final 5/6/2026 Approved DAKOTA LOW
PLUMBING-Final 5/6/2026 Approved DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved DAKOTA LOW
Service/Power Release 5/6/2026 Not Ready for Inspection DAKOTA LOW
Final 5/13/2026 Not Ready for Inspection DAKOTA LOW
Service/Power Release 5/13/2026 Not Ready for Inspection DAKOTA LOW
Final 5/18/2026 OK to Issue CofO DAKOTA LOW
Service/Power Release 5/18/2026 Approved DAKOTA LOW