3619-3621 S MOORE ST 90066

Certificate Information: 3619-3621 S MOORE ST 90066

Application / Permit
25010-10000-02280
Plan Check / Job No.
B25LA21310
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e). To be sprinklered thru-out will NFPA-13D.
Permit Issued
Issued on 8/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 MICHAEL LOPEZ
Assigned to Zoning Architect 5/29/2025 CAMERON JONES
Corrections Issued 6/5/2025 MICHAEL LOPEZ
Quality Review Completed 6/6/2025 KEN GILL
Building Plans Picked Up 6/18/2025 APPLICANT
Plan Check Approved 8/5/2025 MATTHEW TORRES
Issued 8/6/2025 APPLICANT
CofO in Progress 7/20/2026 MICHAEL LEWIS
Permit Finaled 7/20/2026 RICHARD STEINBACH
CofO Issued 7/20/2026 RICHARD STEINBACH
Permit Finaled 7/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/25/2025 KURT CORRAL
Low Impact Development (LID) Cleared 6/26/2025 ERNEST TSE
Address approval Cleared 6/27/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/27/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 6/30/2025 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 7/8/2025 ROSE MARIE SMITH
Sewer availability Cleared 7/8/2025 ROSE MARIE SMITH
Specific Plan Cleared 7/10/2025 EDER ROMERO
Zoning Plan Check Cleared 7/15/2025 MICHAEL LOPEZ
GPI Written Notices Cleared 8/5/2025 MICHAEL LOPEZ
Hold Cleared 8/18/2025 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/8/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 8/20/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/19/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 1/16/2026 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Approved MICHAEL ALLEN
HVAC-Rough 1/16/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/16/2026 Approved MICHAEL ALLEN
ELECTRICAL-Rough 1/22/2026 Approved ANTHONY EGSON
PLUMBING-Rough 1/22/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/23/2026 Approved RUBEN RIVAS
Green Building Rough 1/23/2026 Approved RUBEN RIVAS
Verify Sprinkler Sign Off 1/23/2026 Approved RUBEN RIVAS
Insulation 2/10/2026 Approved TEMISTOCLES CAAL
Shower Pan 2/10/2026 Approved TEMISTOCLES CAAL
Special/Order Compliance 2/10/2026 Partial Inspection HERBERT GIRON
Drywall Nailing 2/17/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 2/17/2026 Approved DAKOTA LOW
ELECTRICAL-Final 6/25/2026 Approved DAKOTA LOW
Green Building Final 6/25/2026 Approved DAKOTA LOW
HVAC-Final 6/25/2026 Not Ready for Inspection DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV Approved DAKOTA LOW
Service/Power Release 6/25/2026 Not Ready for Inspection DAKOTA LOW
Smoke Detectors 6/25/2026 Approved DAKOTA LOW
HVAC-Final 7/1/2026 Approved DAKOTA LOW
PLUMBING-Final 7/1/2026 Approved DAKOTA LOW
Final 7/17/2026 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 7/17/2026 Approved MICHAEL LEWIS