1241 N BIENVENEDA AVE 90272
Certificate Information: 1241 N BIENVENEDA AVE 90272
- Application / Permit
- 25010-10000-02228
- Plan Check / Job No.
- B25LA20980
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, FACTORY BUILT
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | KEVIN MORALES |
| Corrections Issued | 5/29/2025 | KEVIN MORALES |
| Quality Review Completed | 6/2/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/31/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 8/22/2025 | KEVIN MORALES |
| Plan Check Approved | 9/5/2025 | KEVIN MORALES |
| Plan Check Approved | 9/8/2025 | JAZMIN OLMOS |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/5/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 6/5/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 6/5/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 6/5/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 6/5/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 6/10/2025 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 6/17/2025 | JERRY KAO |
| Trees in Parkway | Cleared | 7/7/2025 | MIGUEL ORNELAS |
| Permit | Cleared | 8/4/2025 | TREVOR QUAN |
Contact Information
| Contractor | Arya Group Inc; Lic. No.: 694649-B | 10490 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/11/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 9/11/2025 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 9/12/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 9/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 9/12/2025 | Corrections Issued | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 9/15/2025 | Conditional Approval | BOBBY KEY |
| Service/Power Release | 12/9/2025 | Corrections Issued | BOBBY KEY |
| Service/Power Release | 12/17/2025 | Approved | BOBBY KEY |
| Sewer | 12/17/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/13/2026 | Partial Approval | BOBBY KEY |
| Final | 1/13/2026 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/13/2026 | Approved | BOBBY KEY |
| Green Building Final | 1/13/2026 | Approved | BOBBY KEY |
| Green Building Rough | 1/13/2026 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 1/13/2026 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 1/13/2026 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 2/4/2026 | Corrections Issued | BOBBY KEY |