4628 N SALOMA AVE 91403

Certificate Information: 4628 N SALOMA AVE 91403

Application / Permit
25010-10000-02176
Plan Check / Job No.
B25LA19727
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - NEW 1 STORY SFD PER SB9 TWO UNIT DEVELOPMENT, SEE COMMENTS
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 STARR CHEN
Corrections Issued 5/20/2025 STARR CHEN
Quality Review Completed 5/20/2025 EUGENE BARBEAU
Assigned to Zoning Architect 5/22/2025 RYAN DEL POSO
Plan Check Approved 8/8/2025 STARR CHEN
Issued 8/14/2025 APPLICANT
CofO in Progress 6/3/2026 RAUL OLAGI
CofO Issued 6/9/2026 RUBEN SALAS
Permit Finaled 6/9/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/30/2025 GILBERT URREA
Senate Bill 9 Cleared 6/11/2025 ALEX VELA
Address approval Cleared 6/12/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/17/2025 TREVOR QUAN
Sewer availability Cleared 6/17/2025 TREVOR QUAN
Construction near power lines Cleared 6/23/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 6/24/2025 TREVOR QUAN
Miscellaneous Cleared 7/21/2025 MAX LODER
Zoning Plan Check Cleared 7/24/2025 RYAN DEL POSO

Contact Information

Contractor Owner-Builder       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: C92714 331 ARDEN AVE SUIT 201      GLENDALE, CA 91203

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 10/28/2025 Approved JACK KARGODORIAN
Wood Frame 10/28/2025 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 11/21/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 11/25/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/2/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 12/2/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/3/2025 Not Ready for Inspection LOUIS ESCOTO
Shower Pan 12/3/2025 Approved LOUIS ESCOTO
ELECTRICAL-Rough 12/4/2025 Approved JACK KARGODORIAN
Shower Pan 12/8/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/12/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/16/2025 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 12/16/2025 Approved JACK KARGODORIAN
Insulation 12/18/2025 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 12/18/2025 Partial Approval JACK KARGODORIAN
Insulation 12/22/2025 Corrections Issued JACK KARGODORIAN
Drywall Nailing 1/12/2026 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 5/13/2026 Not Ready for Inspection MISAEL ESPARZA
Final 5/13/2026 Corrections Issued MISAEL ESPARZA
Green Building Final 5/13/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/13/2026 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 5/13/2026 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/13/2026 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 5/13/2026 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/19/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/19/2026 Not Ready for Inspection MISAEL ESPARZA
Final 5/19/2026 Corrections Issued MISAEL ESPARZA
Green Building Final 5/19/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/19/2026 Approved MISAEL ESPARZA
HVAC-Final 5/19/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 5/19/2026 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved MISAEL ESPARZA
Service/Power Release 5/19/2026 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 5/19/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/26/2026 Approved RAUL OLAGI
Final 5/26/2026 Corrections Issued RAUL OLAGI
Green Building Final 5/26/2026 Approved RAUL OLAGI
HVAC-Final 5/26/2026 Approved RAUL OLAGI
Final 6/3/2026 OK to Issue CofO RAUL OLAGI