832 N ENCHANTED WAY 90272

Certificate Information: 832 N ENCHANTED WAY 90272

Application / Permit
25010-10000-02160
Plan Check / Job No.
B25LA20346
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND ADDITION SUPPLEMENTAL TO 20014-10000-03000.
Permit Issued
Issued on 7/24/2025
Issuing Office
Current Status
Issued on 7/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 KEVIN MORALES
Corrections Issued 6/3/2025 KEVIN MORALES
Quality Review Completed 6/3/2025 EUGENE BARBEAU
Plan Check Approved 7/16/2025 KEVIN MORALES
Issued 7/24/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2025 CINDY QI
Roof/Waste drainage to street Cleared 6/3/2025 CINDY QI
Sewer availability Cleared 6/3/2025 CINDY QI
Hydrant and Access approval Cleared 6/26/2025 PATRICK PEREZ

Contact Information

Contractor Call Bryce Construction Inc; Lic. No.: 675054-B P O BOX 220053      NEWHALL, CA 91322

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2025 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 10/15/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 12/23/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 1/6/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval BOBBY KEY
Deputy Wood Construction 3/2/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 4/30/2026 No Access for Inspection BOBBY KEY
ELECTRICAL-Rough 4/30/2026 No Access for Inspection BOBBY KEY
Green Building Rough 4/30/2026 No Access for Inspection BOBBY KEY
HVAC-Rough 4/30/2026 No Access for Inspection BOBBY KEY
PLUMBING-Rough 4/30/2026 No Access for Inspection BOBBY KEY
Verify Sprinkler Sign Off 4/30/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 5/6/2026 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 5/6/2026 Corrections Issued MICHAEL ALLEN
Gas Test 5/6/2026 Approved MICHAEL ALLEN
Green Building Rough 5/6/2026 Partial Approval MICHAEL ALLEN
HVAC-Rough 5/6/2026 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 5/6/2026 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 5/6/2026 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 5/13/2026 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 5/18/2026 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 5/18/2026 Partial Approval DANIEL VERA
Green Building Rough 5/18/2026 Not Ready for Inspection DANIEL VERA
HVAC-Rough 5/18/2026 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 5/27/2026 No Access for Inspection DANIEL VERA
Green Building Rough 5/27/2026 No Access for Inspection DANIEL VERA
HVAC-Rough 5/27/2026 No Access for Inspection DANIEL VERA
BUILDING-Rough-Frame 5/29/2026 Corrections Issued DANIEL VERA
HVAC-Rough 5/29/2026 Approved DANIEL VERA