10317 W LORENZO DR 90064
Certificate Information: 10317 W LORENZO DR 90064
- Application / Permit
- 25010-10000-02158
- Plan Check / Job No.
- B25LA17432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- detached ADU
- Permit Issued
- Issued on 10/9/2025
- Issuing Office
- Current Status
- Issued on 10/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 5/16/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/3/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/14/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/6/2025 | ARSALAN SHABESTARI |
| Issued | 10/9/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/11/2025 | HAMID GHAEMMAGHAMI |
| Address approval | Cleared | 6/12/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/12/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/13/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/17/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/30/2025 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 8/16/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 8/16/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Ambar Construction; Lic. No.: 1021891-B | , |
| Contractor | Ambar Inc; Lic. No.: 1021891-B | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 12/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Subgrade | 12/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/4/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/4/2025 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 12/4/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/5/2025 | Partial Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 12/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Final | 12/11/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Subgrade | 12/11/2025 | Approved | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 12/12/2025 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | ASHLEY THOMPSON |
| Deputy Steel/Welding | 5/8/2026 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 5/11/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 5/29/2026 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/29/2026 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 5/29/2026 | Approved | KIRK SANDERS |
| Special/Order Compliance | 5/29/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 6/1/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 6/4/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Sewer | 6/5/2026 | Approved | BOBBY KEY |
| Underground Mechanical | 6/9/2026 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/1/2026 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 7/1/2026 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 7/1/2026 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 7/1/2026 | Approved | ASHLEY THOMPSON |