2000 N FULLER AVE 90046
Certificate Information: 2000 N FULLER AVE 90046
- Application / Permit
- 25010-10000-02144
- Plan Check / Job No.
- B25LA20140
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan: Proposed 1-story pre-fab restroom building.
- Permit Issued
- Issued on 12/3/2025
- Issuing Office
- Current Status
- Issued on 12/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 6/5/2025 | KAREN MEZA-MORALES |
| Corrections Issued | 6/16/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 6/23/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 11/4/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 11/18/2025 | MICHAEL LOPEZ |
| Issued | 12/3/2025 | APPLICANT |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 6/30/2025 | MASON NG |
| Zoning Plan Check | Cleared | 7/2/2025 | KAREN MEZA-MORALES |
| Flood clearance | Cleared | 7/21/2025 | TUYEN LE |
| Low Impact Development (LID) | Cleared | 7/29/2025 | ERNEST TSE |
| Green Code | Cleared | 8/27/2025 | Daniel Smiley |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2025 | CELINA MORENO |
| GPI Written Notices | Cleared | 9/9/2025 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 9/9/2025 | ROBERT PINA |
| DAS Clearance | Cleared | 9/12/2025 | ELIZABETH TOMS |
| Metro Rail approval | Cleared | 10/3/2025 | MICHAEL LOPEZ |
Contact Information
| Architect | Brett,, Richard Patrick; Lic. No.: NA31256 | , |
| Contractor | Childs Play; Lic. No.: 741617-B | , |
| Contractor | Chris Kelley Inc; Lic. No.: 741617-B | , |
| Engineer | Quinton,, Brandon Nicholas; Lic. No.: C93818 | 954 COBBLESTONE DRIVE HEBER CITY, UT 84032 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2026 | Approved | MARTIN TAVITIAN |